Differences between revisions 320 and 348 (spanning 28 versions)
Revision 320 as of 2018-03-01 09:30:38
Size: 9633
Comment:
Revision 348 as of 2018-03-19 09:34:15
Size: 9914
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/3/1(Thur.) 2017/3/19(Mon.)
Line 56: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura
Line 58: Line 55:
 * Report of work (*:responsible person) ==== Report of work (*:responsible person) ====
Line 60: Line 57:
  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * VAC: *Uchiyama, Kimura, Suzuki
  * 4-5 turbo pumps started.
   * Currently vacuum level is ~1e-4Pa.
   * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
  * New control boxes for gate valve test were done.
   * Currently they work at local place, but they will be controlled remotely in the future.
  * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
  * PR2 assembly frames will be removed soon.
  * Power cable was connected to the ground at the power panel and made a short to the ground.
Line 70: Line 68:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.

  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
Line 78: Line 70:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
==== Work plan (*:responsible person) ====
Line 81: Line 72:
  * CRY: mirror temperature ~94K.  * Alignment, ETMY: *Izumi
  * All alignment after pump down will be checked.
  * PR3 yaw had some drift during pump-down.
Line 84: Line 77:
 * Work plan (*:responsible person)  * Cal:
  * Calibration test using MC is planned on Wednesday.
Line 86: Line 80:
  * Alignment:
   * IMMT and MC will be aligned to center PRs.

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.

 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * VAC: Kimura, Sawada
  * Door will be closed at 3/23.
  * EX PD will be removed simonteninaously.: *Yokozawa
Line 110: Line 85:
==== Laser hazard ====
 * [AM] IR: all, Green: off.
 * [PM] IR: all, Green: off.
 * [night] IR: all, Green: off

==== Weekly ====

 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.

 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 111: Line 102:
Line 117: Line 109:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 114:
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 139:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/19(Mon.)

  • Remote participants by eZuce: Kimura

Report of work (*:responsible person)

  • VAC: *Uchiyama, Kimura, Suzuki
    • 4-5 turbo pumps started.
      • Currently vacuum level is ~1e-4Pa.
      • Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
    • New control boxes for gate valve test were done.
      • Currently they work at local place, but they will be controlled remotely in the future.
    • Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
    • PR2 assembly frames will be removed soon.
    • Power cable was connected to the ground at the power panel and made a short to the ground.

Work plan (*:responsible person)

  • Alignment, ETMY: *Izumi
    • All alignment after pump down will be checked.
    • PR3 yaw had some drift during pump-down.
  • Cal:
    • Calibration test using MC is planned on Wednesday.
  • VAC: Kimura, Sawada
    • Door will be closed at 3/23.
    • EX PD will be removed simonteninaously.: *Yokozawa

Laser hazard

  • [AM] IR: all, Green: off.
  • [PM] IR: all, Green: off.
  • [night] IR: all, Green: off

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)