Differences between revisions 320 and 355 (spanning 35 versions)
Revision 320 as of 2018-03-01 09:30:38
Size: 9633
Comment:
Revision 355 as of 2018-03-23 09:22:15
Size: 10003
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/3/1(Thur.) 2017/3/23(Fri.)
Line 56: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Izumi, Miyoki
Line 58: Line 55:
 * Report of work (*:responsible person) ==== Report of work (*:responsible person) ====
Line 60: Line 57:
  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * IFO: *Izumi, Miyamoto, Eleonora
  * BS had some difficulty to close control loop of Y of oplev.
  * T of ETMY control loop was closed.
  * Circuits of baffle PD are being prepared.

 * AOS: *Akutsu, Yokogawa
  * Green team succeeded to reach green and IR to ETMY.
  * BRT alignment is going on yesterday and today.
  * Oplev is being prepared at EXC.

 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.
Line 70: Line 72:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.
==== Work plan (*:responsible person) ====
Line 73: Line 74:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
 * Alignment: *Eleonora, Miyamoto
  * BS diagonalization
  * ETMY damping

 * AOS: *Akutsu, Yokogawa
  * BRT alignment is going on yesterday and today.
  * Oplev work at EXC.
Line 78: Line 83:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
==== Laser hazard ====
 * [AM]
  * IR: PSL
  * Green: around PR2
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.
Line 81: Line 91:
  * CRY: mirror temperature ~94K.  * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.
Line 83: Line 95:
==== Weekly ====
Line 84: Line 97:
 * Work plan (*:responsible person)  * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa
Line 86: Line 103:
  * Alignment:
   * IMMT and MC will be aligned to center PRs.

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.

 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * week of 3/26
  * Rough alignment of ETMX is planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 111: Line 108:
Line 117: Line 115:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 120:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/23(Fri.)

  • Remote participants by eZuce: Izumi, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • BS had some difficulty to close control loop of Y of oplev.
    • T of ETMY control loop was closed.
    • Circuits of baffle PD are being prepared.
  • AOS: *Akutsu, Yokogawa
    • Green team succeeded to reach green and IR to ETMY.
    • BRT alignment is going on yesterday and today.
    • Oplev is being prepared at EXC.
  • Camera: Yokozawa, Yamamoto, Miyamoto
    • X end camera will be recovered.
    • IYC cooling started.

Work plan (*:responsible person)

  • Alignment: *Eleonora, Miyamoto
    • BS diagonalization
    • ETMY damping
  • AOS: *Akutsu, Yokogawa
    • BRT alignment is going on yesterday and today.
    • Oplev work at EXC.

Laser hazard

  • [AM]
    • IR: PSL
    • Green: around PR2
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX is planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings