Differences between revisions 320 and 372 (spanning 52 versions)
Revision 320 as of 2018-03-01 09:30:38
Size: 9633
Comment:
Revision 372 as of 2018-04-06 09:10:54
Size: 10529
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/6(Fri.) ===
Line 54: Line 52:
2017/3/1(Thur.) * Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Line 56: Line 54:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
 * IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
  * Both light was confirmed at ETMX last night.
  * BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz.
  * Connection between k1lsc and k1bs is still something wrong.
  * Quality of ETMX looks much better than EMY. No bright spot was seen.
Line 58: Line 61:
 * Report of work (*:responsible person)

  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * ETMY: *Miyamoto
  * Covered on Oplev.
Line 70: Line 65:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.
==== Work plan (*:responsible person) ====
 * Alignment: Izumi
  * No light is used in the daytime. Start using beam from evening.
Line 73: Line 69:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
 * DAQ: *Miyakawa
  * Memory will be increased today. SSD might be tested today at k1tw0.

 * Vacuum: *Kimura
  * Closing door will be performed in the next week as planned.
Line 78: Line 76:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 81: Line 84:
  * CRY: mirror temperature ~94K. * [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 84: Line 89:
 * Work plan (*:responsible person) ==== Weekly ====
Line 86: Line 91:
  * Alignment:
   * IMMT and MC will be aligned to center PRs.
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
  * 4/5 12:30 at fan hut: Meeting before pump down 1
Line 89: Line 96:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.  * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
Line 91: Line 100:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
==== Issues ====
Line 110: Line 103:
 * Issues
Line 117: Line 109:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 114:
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 142:
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/6(Fri.)

* Remote participants by eZuce: Kimura, Miyoki, Yokozawa

Report of work (*:responsible person)

  • IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
    • Both light was confirmed at ETMX last night.
    • BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz.
    • Connection between k1lsc and k1bs is still something wrong.
    • Quality of ETMX looks much better than EMY. No bright spot was seen.
  • ETMY: *Miyamoto
    • Covered on Oplev.

Work plan (*:responsible person)

  • Alignment: Izumi
    • No light is used in the daytime. Start using beam from evening.
  • DAQ: *Miyakawa
    • Memory will be increased today. SSD might be tested today at k1tw0.
  • Vacuum: *Kimura
    • Closing door will be performed in the next week as planned.

Laser hazard

* [AM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [PM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [night]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

Weekly

  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
    • 4/5 12:30 at fan hut: Meeting before pump down 1
  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)