Differences between revisions 320 and 382 (spanning 62 versions)
Revision 320 as of 2018-03-01 09:30:38
Size: 9633
Comment:
Revision 382 as of 2018-04-11 12:29:14
Size: 10810
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/11(Wed.) ===
Line 54: Line 52:
2017/3/1(Thur.) * Remote participants by eZuce: None
Line 56: Line 54:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
 * IFO: Enomoto, Nagano, Nagano
  * RF signal was extracted from fringe of Michelson.
  * Ratio of ETMY and ETMX is not so large, roughly 1:1.
  * We need more damping for both ETMY and ETMX.
  * 4 front gate valve will be open.
  * Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD.
Line 58: Line 62:
 * Report of work (*:responsible person)  * Camera: Yokozawa
  * Illuminator at X end chamber was installed.
Line 60: Line 65:
  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * DAQ: Miyakawa, Yamamoto
  * k1tw0 started writing minute raw data.

==== Work plan (*:responsible person) ====
 * Camera: Inoue, Yokozawa
  * We check that nothing blocks the beam between EXA and EXC.

 * DAQ: *Miyakawa
  * Preparation to move writing minute raw of k1fw1 to a new k1tw1.

==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: PSL, Yend 1F
  * Green: off

 * [night]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 70: Line 88:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.
==== Weekly ====
Line 73: Line 90:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson
  * 4/13~ Pump down

 * week of 4/16
  * Michelson control
  * Leak check

 * week of 4/23
  * Operation

==== Issues ====
Line 78: Line 106:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.

  * CRY: mirror temperature ~94K.


 * Work plan (*:responsible person)

  * Alignment:
   * IMMT and MC will be aligned to center PRs.

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.

 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.


 * Issues
Line 117: Line 112:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 117:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 146:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/11(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: Enomoto, Nagano, Nagano
    • RF signal was extracted from fringe of Michelson.
    • Ratio of ETMY and ETMX is not so large, roughly 1:1.
    • We need more damping for both ETMY and ETMX.
    • 4 front gate valve will be open.
    • Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD.
  • Camera: Yokozawa
    • Illuminator at X end chamber was installed.
  • DAQ: Miyakawa, Yamamoto
    • k1tw0 started writing minute raw data.

Work plan (*:responsible person)

  • Camera: Inoue, Yokozawa
    • We check that nothing blocks the beam between EXA and EXC.
  • DAQ: *Miyakawa
    • Preparation to move writing minute raw of k1fw1 to a new k1tw1.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: PSL, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC
    • Some controls for Michelson
    • 4/13~ Pump down
  • week of 4/16
    • Michelson control
    • Leak check
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)