Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/16(Mon.) ===
Line 54: Line 52:
2017/3/1(Thur.) * Remote participants by eZuce: Miyoki
Line 56: Line 54:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
 * VAC: *Kimura
  * Pump down started ~10am.
Line 58: Line 58:
 * Report of work (*:responsible person)  * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Beams from ETMX and ETMY were seen at REFL and showed some interference.
Line 60: Line 61:
  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * DAQ: *Miyakawa
  * k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend.

==== Work plan (*:responsible person) ====
 * Extended chief meeting at Toyama Univ.

 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 70: Line 71:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.
==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 73: Line 79:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
 * [night]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 78: Line 84:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
==== Weekly ====
Line 81: Line 86:
  * CRY: mirror temperature ~94K.  * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 83: Line 91:
 * week of 4/23
  * Operation
Line 84: Line 94:
 * Work plan (*:responsible person)

  * Alignment:
   * IMMT and MC will be aligned to center PRs.

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.

 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.


 * Issues
==== Issues ====
Line 117: Line 101:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 106:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 135:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/16(Mon.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • VAC: *Kimura
    • Pump down started ~10am.
  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Beams from ETMX and ETMY were seen at REFL and showed some interference.
  • DAQ: *Miyakawa
    • k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend.

Work plan (*:responsible person)

  • Extended chief meeting at Toyama Univ.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1