Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 27: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 53: Line 39:
=== 2018/4/28(Sat.) ===
Line 54: Line 41:
2017/3/1(Thur.) * Remote participants by eZuce: None
* 1st day of Phase 1 operation
 * OLG by
Line 56: Line 45:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
Line 58: Line 47:
 * Report of work (*:responsible person)

  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * IFO: *Izumi, Enomoto + many
  * ETMY damping filter was back to what was best. Fluctuation is ~1urad.
  * ETMX damping filter changed a bit. Fluctuation is < 1urad.
  * BS alignment noise was improved around 10-30Hz 8 at most.
  * Gain bump can be seen around UGF of MICH.
  * Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist.
Line 70: Line 55:
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.
 * Camera: Yokozawa, Inoue
  * IYA camera could not see BS, because some clipping may exist.
Line 73: Line 58:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
 * WAB: Akutsu
  * Heater off.

 * IYC: Tomaru
  * Cooler off.

 * Operaton:
  * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened.

==== Work plan (*:responsible person) ====

 * CAL: Yamamoto
  * Optical gain measurement
  * Open loot TF.
  * Amplitude tuning for injection.
  * Sensitivity.
  * BS to MICH TF, if can.

 * IFO: *Izumi, Enomoto + many
  * Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board.
Line 78: Line 80:
  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 81: Line 88:
  * CRY: mirror temperature ~94K.  * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 84: Line 93:
 * Work plan (*:responsible person) ==== Weekly ====
Line 86: Line 95:
  * Alignment:
   * IMMT and MC will be aligned to center PRs.
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 89: Line 99:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.  * week of 4/30
  * Operation continues.
Line 91: Line 102:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
==== Issues ====
Line 110: Line 105:
 * Issues
Line 117: Line 111:
==== Weekly meeting ==== === Weekly meeting ===
Line 122: Line 116:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 145: Line 146:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/28(Sat.)

* Remote participants by eZuce: None * 1st day of Phase 1 operation

  • OLG by

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • ETMY damping filter was back to what was best. Fluctuation is ~1urad.
    • ETMX damping filter changed a bit. Fluctuation is < 1urad.

    • BS alignment noise was improved around 10-30Hz 8 at most.
    • Gain bump can be seen around UGF of MICH.
    • Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist.
  • Camera: Yokozawa, Inoue
    • IYA camera could not see BS, because some clipping may exist.
  • WAB: Akutsu
    • Heater off.
  • IYC: Tomaru
    • Cooler off.
  • Operaton:

Work plan (*:responsible person)

  • CAL: Yamamoto
    • Optical gain measurement
    • Open loot TF.
    • Amplitude tuning for injection.
    • Sensitivity.
    • BS to MICH TF, if can.
  • IFO: *Izumi, Enomoto + many
    • Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start
  • week of 4/30
    • Operation continues.

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)