2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/2(Fri.) | 2017/3/15(Thur.) |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. |
Line 65: | Line 64: |
* IOO: kokeyama * Alignment to MC was fixe. |
* BS: Top of the BS chamber was tightened but no big shift was not found. |
Line 68: | Line 66: |
* AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. |
* AOS: IYC and IYA started pumping down. |
Line 72: | Line 68: |
* CRY: mirror temperature 89K. | * ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. * CRY: Mirror reached at 18K. |
Line 75: | Line 74: |
* Work plan (*:responsible person) | ==== Work plan (*:responsible person) ==== |
Line 77: | Line 76: |
* Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. |
* Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. |
Line 80: | Line 80: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | * VAC: Uchiyama * Duct connection. |
Line 82: | Line 83: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
* Camera: Yokozawa * Both door will be closed today. Pump down will be start today. |
Line 87: | Line 86: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
* AOS: IYC will be closed and start pump-down. |
Line 91: | Line 88: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 95: | Line 89: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
==== Laser hazard ==== * [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off ==== Weekly ==== * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 101: | Line 107: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 107: | Line 116: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 112: | Line 121: |
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 135: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/15(Thur.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
- Tuning of ETMY damping is still going on.
- Beam alignment to both end and REFL port was confirmed the last night.
- Beam is now being drifted to down slowly at PSL by ~100urad.
- One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
- When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
- BS: Top of the BS chamber was tightened but no big shift was not found.
- AOS: IYC and IYA started pumping down.
- ETMY: *Enomoto
- BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.
- CRY: Mirror reached at 18K.
Work plan (*:responsible person)
- Alignment: Enomonoto, Izumi
- IMMT coil driver will be checked.
- REFL camera has been placed and will be setup today.
- VAC: Uchiyama
- Duct connection.
- Camera: Yokozawa
- Both door will be closed today. Pump down will be start today.
- AOS: IYC will be closed and start pump-down.
Laser hazard
- [AM] IR: PSL, Green: off.
- [PM] IR: PSL, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/12
- 3/14: meeting for pump-down check
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)