2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/2(Fri.) | 2017/3/23(Fri.) |
Line 56: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Izumi, Miyoki |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. |
* IFO: *Izumi, Miyamoto, Eleonora * BS had some difficulty to close control loop of Y of oplev. * T of ETMY control loop was closed. * Circuits of baffle PD are being prepared. |
Line 65: | Line 62: |
* IOO: kokeyama * Alignment to MC was fixe. |
* AOS: *Akutsu, Yokogawa * Green team succeeded to reach green and IR to ETMY. * BRT alignment is going on yesterday and today. * Oplev is being prepared at EXC. |
Line 68: | Line 67: |
* AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. * CRY: mirror temperature 89K. |
* Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 75: | Line 72: |
* Work plan (*:responsible person) | ==== Work plan (*:responsible person) ==== |
Line 77: | Line 74: |
* Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. |
* Alignment: *Eleonora, Miyamoto * BS diagonalization * ETMY damping |
Line 80: | Line 78: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. * Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* AOS: *Akutsu, Yokogawa * BRT alignment is going on yesterday and today. * Oplev work at EXC. |
Line 100: | Line 83: |
==== Laser hazard ==== * [AM] * IR: PSL * Green: around PR2 * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. ==== Weekly ==== * week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa * week of 3/26 * Rough alignment of ETMX is planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 101: | Line 108: |
Line 107: | Line 115: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 112: | Line 120: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 135: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/23(Fri.)
- Remote participants by eZuce: Izumi, Miyoki
Report of work (*:responsible person)
- IFO: *Izumi, Miyamoto, Eleonora
- BS had some difficulty to close control loop of Y of oplev.
- T of ETMY control loop was closed.
- Circuits of baffle PD are being prepared.
- AOS: *Akutsu, Yokogawa
- Green team succeeded to reach green and IR to ETMY.
- BRT alignment is going on yesterday and today.
- Oplev is being prepared at EXC.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- Alignment: *Eleonora, Miyamoto
- BS diagonalization
- ETMY damping
- AOS: *Akutsu, Yokogawa
- BRT alignment is going on yesterday and today.
- Oplev work at EXC.
Laser hazard
- [AM]
- IR: PSL
- Green: around PR2
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21~: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX is planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools