Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/2(Fri.) | 2017/3/26(Mon.) |
Line 56: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Shoda |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. |
* ETMY: *Miyamoto * Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close! |
Line 65: | Line 60: |
* IOO: kokeyama * Alignment to MC was fixe. |
* BS: *Eleonora, Yamamoto * DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently. |
Line 68: | Line 63: |
* AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. |
* Camera: *Inoue * X end camera was recovered, needs PC tuning. |
Line 72: | Line 66: |
* CRY: mirror temperature 89K. | * Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 75: | Line 71: |
* Work plan (*:responsible person) | ==== Work plan (*:responsible person) ==== |
Line 77: | Line 73: |
* Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. |
* BS: *Enomonot * Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week. |
Line 80: | Line 76: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | * AOS: *Akutsu, Yokogawa * BRT alignment is still going on. * Oplev work at EXC. It will be available early this week. |
Line 82: | Line 80: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
|
Line 87: | Line 81: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
==== Laser hazard ==== * [AM] * IR: PSL * Green: none * [PM] * IR: PSL * Green: none |
Line 91: | Line 89: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* [night] * IR: PSL * Green: none |
Line 95: | Line 93: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
==== Weekly ==== * week of 3/26 * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * EX PD will be removed.: *Yokozawa * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
Line 101: | Line 110: |
Line 107: | Line 117: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 112: | Line 122: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 135: | Line 148: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/26(Mon.)
- Remote participants by eZuce: Shoda
Report of work (*:responsible person)
- ETMY: *Miyamoto
- Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
- BS: *Eleonora, Yamamoto
- DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.
- Camera: *Inoue
- X end camera was recovered, needs PC tuning.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- BS: *Enomonot
- Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
- AOS: *Akutsu, Yokogawa
- BRT alignment is still going on.
- Oplev work at EXC. It will be available early this week.
Laser hazard
- [AM]
- IR: PSL
- Green: none
- [PM]
- IR: PSL
- Green: none
- [night]
- IR: PSL
- Green: none
Weekly
- week of 3/26
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- EX PD will be removed.: *Yokozawa
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)