8872
Comment:
|
10477
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/2(Fri.) | 2017/3/29(Thur.) |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Jump of GAS filter was compensated and fixed. * Yaw was roughly aligned by top filter. * First contact was removed. * Top chamber was closed. * Beam reached at the ETMX. * Baffle PD was tested well. |
Line 65: | Line 65: |
* IOO: kokeyama * Alignment to MC was fixe. |
* BS: *Enomoto * We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch. |
Line 68: | Line 68: |
* AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. |
* BRT: Akutsu * Light is collimated well. |
Line 72: | Line 71: |
* CRY: mirror temperature 89K. | * Camera: Yokozawa * EX camera takes every one hour. * Needs 1 sec picture in the weekend. ==== Work plan (*:responsible person) ==== * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Mirror will be aligned with beam today. * CAL: *Yamamoto * CAL model is tested using iMC. |
Line 75: | Line 84: |
* Work plan (*:responsible person) | ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 77: | Line 92: |
* Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 80: | Line 96: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | ==== Weekly ==== |
Line 82: | Line 98: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 87: | Line 104: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
Line 91: | Line 108: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* week of 4/9 * Closing EXC |
Line 95: | Line 111: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
==== Issues ==== |
Line 99: | Line 113: |
* BS: DAC had some glitches with no output (even dac kill and master SW are off). | |
Line 100: | Line 115: |
* Issues | |
Line 107: | Line 121: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 112: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 135: | Line 153: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/29(Thur.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Jump of GAS filter was compensated and fixed.
- Yaw was roughly aligned by top filter.
- First contact was removed.
- Top chamber was closed.
- Beam reached at the ETMX.
- Baffle PD was tested well.
- BS: *Enomoto
- We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch.
- BRT: Akutsu
- Light is collimated well.
- Camera: Yokozawa
- EX camera takes every one hour.
- Needs 1 sec picture in the weekend.
Work plan (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Mirror will be aligned with beam today.
- CAL: *Yamamoto
- CAL model is tested using iMC.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches with no output (even dac kill and master SW are off).
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools