Size: 8872
Comment:
|
Size: 11821
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/25(Wed.) === | |
Line 54: | Line 52: |
2017/3/2(Fri.) | * Remote participants by eZuce: None |
Line 56: | Line 54: |
* Remote participants by eZuce: None | ==== Report of work (*:responsible person) ==== |
Line 58: | Line 56: |
* Report of work (*:responsible person) | * IFO: *Izumi, Enomoto, Nakano + many * Michelson lock lasted ~40min with Guardian. * ETMX had some drift. It may cause lock down. |
Line 60: | Line 60: |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. |
* Modulation frequency was not tuned yet to iMC length. * Measurement of AM conversion can know the matching of mod. freq. to iMC length. |
Line 65: | Line 63: |
* IOO: kokeyama * Alignment to MC was fixe. |
* PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser. |
Line 68: | Line 65: |
* AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. |
* BS: *Eleonora, Izumi, Arai * BS IM feed back was engaged. * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control. * Gain of some loops of oplev servo changed stronger. |
Line 72: | Line 70: |
* CRY: mirror temperature 89K. | * CAL: *Yamamoto, Enomoto, Izumi * Optical measumremnt was measured. * Sensitivity is shown in the control room, being calculated from H(t). * Injection: *Miyamoto, Yokozawa * Noise budget: *Michimura, Enomoto * IOO: *Kokeyama, Enomoto * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control. * ETMX: *Hasegawa, Nakano, Enomoto * ETMX has some drift for 10-20urad. * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto * ETMY need L damping. * Gardian was implemented. |
Line 75: | Line 89: |
* Work plan (*:responsible person) | ==== Work plan (*:responsible person) ==== |
Line 77: | Line 91: |
* Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. |
* BS: *Eleonora, Izumi, Arai * Opleve loop gains will change stronger. |
Line 80: | Line 94: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | * CAL: *Yamamoto, Enomoto, Izumi * Cal signal will be injected. |
Line 82: | Line 97: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
Line 100: | Line 101: |
* Issues | ==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/23 * Michelson control. * 4/28 Operation start ==== Issues ==== |
Line 107: | Line 128: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 112: | Line 133: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 135: | Line 163: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/25(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Michelson lock lasted ~40min with Guardian.
- ETMX had some drift. It may cause lock down.
- Modulation frequency was not tuned yet to iMC length.
- Measurement of AM conversion can know the matching of mod. freq. to iMC length.
- PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
- Michelson lock lasted ~40min with Guardian.
- BS: *Eleonora, Izumi, Arai
- BS IM feed back was engaged.
- Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
- Gain of some loops of oplev servo changed stronger.
- BS IM feed back was engaged.
- CAL: *Yamamoto, Enomoto, Izumi
- Optical measumremnt was measured.
- Sensitivity is shown in the control room, being calculated from H(t).
- Injection: *Miyamoto, Yokozawa
- Noise budget: *Michimura, Enomoto
- IOO: *Kokeyama, Enomoto
- MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
- ETMX: *Hasegawa, Nakano, Enomoto
- ETMX has some drift for 10-20urad.
- ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
- ETMY need L damping.
- Gardian was implemented.
Work plan (*:responsible person)
- BS: *Eleonora, Izumi, Arai
- Opleve loop gains will change stronger.
- CAL: *Yamamoto, Enomoto, Izumi
- Cal signal will be injected.
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools