9055
Comment:
|
11650
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/20(Fri.) === | |
Line 54: | Line 52: |
2017/3/5(Mon.) | * Remote participants by eZuce: None |
Line 56: | Line 54: |
* Remote participants by eZuce: Izumi | ==== Report of work (*:responsible person) ==== * Phase 1 operation was postponed to 4/28 start and 5/6 end. |
Line 58: | Line 57: |
* Report of work (*:responsible person) | * VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. |
Line 60: | Line 62: |
* Alignment: Enomoto, Miyo, Yokozawa * We found beam at the IYA but it is not clear PR or BS is misaligned. |
* VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. |
Line 63: | Line 65: |
* IOO: * IMMT2 cannot be seen by camera. We will work on camera this week. |
* ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. |
Line 66: | Line 69: |
* CRY: mirror temperature 71K. | * ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. |
Line 68: | Line 74: |
* Work plan (*:responsible person) * Alignment: Enomoto * We will find beam at the ETMY or ETMX by dithering PR3. * BS: Mark * We lift up the optical table and change items to vacuum compatible one. It does not change BS alignment an oplev. |
* BS: *Eleonora, Izumi * Implementation of L2P filter worked well and they are well decoupled now! * Global injection point for length control is ready. |
Line 77: | Line 79: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | |
Line 79: | Line 80: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
==== Work plan (*:responsible person) ==== |
Line 84: | Line 82: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
Line 88: | Line 85: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. |
Line 92: | Line 88: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. |
Line 97: | Line 92: |
* Issues | * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. ==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/16 * Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. * week of 4/23 * Michelson control. * 4/28 Operation start ==== Issues ==== |
Line 104: | Line 129: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 109: | Line 134: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 133: | Line 164: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/20(Fri.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- Phase 1 operation was postponed to 4/28 start and 5/6 end.
- VAC: *Kimura
- Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
- Pump down started 15:50 yesterday.
- Now vacuum gage shows ~30Pa.
- VAC: *Inoue, Yokozawa
- Vacuum monitor is ready! except for Y arm monitor.
- ETMX: *Hasegawa
- 0.07Hz was damped well!
Yaw and pitch are < 1urad.
- ETMY: *Nakano, Shishido
- Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
- Possibility of heat link for 1.6Hz still remains.
- Beam at REFL seemed to be OK.
- BS: *Eleonora, Izumi
- Implementation of L2P filter worked well and they are well decoupled now!
- Global injection point for length control is ready.
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Leak test will be performed and the gate valve will open on weekend if no problem.
- Camera: *Inoue, Yokozawa
- Tcam of Y end will be ready today.
- We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
- DMG needs some maintenance for DAQ.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check, and fix leaks.
- Opening the last gate valve weekend.
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools