Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/6(Tue.) | 2017/3/26(Mon.) |
Line 56: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Shoda |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto * Beam was found again at PD and Tcam of ETMX and Tcam of ETMY. Baffle PD at |
* ETMY: *Miyamoto * Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close! |
Line 63: | Line 60: |
* BS: Mark * We lifted up the optical table. |
* BS: *Eleonora, Yamamoto * DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently. |
Line 66: | Line 63: |
* IOO: * IMMT2 cannot be seen by camera. We will work on camera this week. |
* Camera: *Inoue * X end camera was recovered, needs PC tuning. |
Line 69: | Line 66: |
* CRY: mirror temperature 71K. | * Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 71: | Line 70: |
* Work plan (*:responsible person) | |
Line 73: | Line 71: |
* Alignment: Enomoto * We will find beam at the ETMY or ETMX by dithering PR3. |
==== Work plan (*:responsible person) ==== |
Line 76: | Line 73: |
* AOS: Akutsu, Michimura * Items PR2 chamber will be replaced, and green light will be used in the afternoon. * WAB work at the IYA. |
* BS: *Enomonot * Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week. |
Line 80: | Line 76: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end for both IR and green. | * AOS: *Akutsu, Yokogawa * BRT alignment is still going on. * Oplev work at EXC. It will be available early this week. |
Line 82: | Line 80: |
* Weekly | |
Line 84: | Line 81: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
==== Laser hazard ==== * [AM] * IR: PSL * Green: none * [PM] * IR: PSL * Green: none |
Line 88: | Line 89: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* [night] * IR: PSL * Green: none |
Line 92: | Line 93: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
==== Weekly ==== * week of 3/26 * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * EX PD will be removed.: *Yokozawa * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
Line 99: | Line 110: |
Line 105: | Line 117: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 110: | Line 122: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 134: | Line 149: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/26(Mon.)
- Remote participants by eZuce: Shoda
Report of work (*:responsible person)
- ETMY: *Miyamoto
- Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
- BS: *Eleonora, Yamamoto
- DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.
- Camera: *Inoue
- X end camera was recovered, needs PC tuning.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- BS: *Enomonot
- Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
- AOS: *Akutsu, Yokogawa
- BRT alignment is still going on.
- Oplev work at EXC. It will be available early this week.
Laser hazard
- [AM]
- IR: PSL
- Green: none
- [PM]
- IR: PSL
- Green: none
- [night]
- IR: PSL
- Green: none
Weekly
- week of 3/26
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- EX PD will be removed.: *Yokozawa
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)