Size: 9093
Comment:
|
Size: 9750
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/6(Tue.) | 2017/3/16(Fri.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Kimura | * Remote participants by eZuce: None |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Alignment: Enomoto * Beam was found again at PD and Tcam of ETMX and Tcam of ETMY. Baffle PD at |
* VAC: *Uchiyama, Kimura, Suzuki * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today. |
Line 63: | Line 60: |
* BS: Mark * We lifted up the optical table. |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Yaw damping stared working by changing polarity. * Beam alignment to both end and REFL port was confirmed the last night. * ~10rad shift was seen as usual. * Clipping was fixed by PSL alignment yesterday. * PR3 is being shifted to yaw by pump down by ~300urad. * LSC model as full model started running at k1imc0. Dolhpin will be conected soon. |
Line 66: | Line 68: |
* IOO: * IMMT2 cannot be seen by camera. We will work on camera this week. |
* Camera: Yokozawa * IYAC and IXAC areas are being pumped down. |
Line 69: | Line 71: |
* CRY: mirror temperature 71K. | * CRY: Mirror reached at 18K. |
Line 71: | Line 73: |
* Work plan (*:responsible person) | |
Line 73: | Line 74: |
* Alignment: Enomoto * We will find beam at the ETMY or ETMX by dithering PR3. |
|
Line 76: | Line 75: |
* AOS: Akutsu, Michimura * Items PR2 chamber will be replaced, and green light will be used in the afternoon. * WAB work at the IYA. |
==== Work plan (*:responsible person) ==== |
Line 80: | Line 77: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end for both IR and green. | * VAC: Uchiyama * Pump down. |
Line 82: | Line 80: |
* Weekly | * DGS: *Miyakawa * 10GB network card at dc0 will be replaced. |
Line 84: | Line 83: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
|
Line 88: | Line 84: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
==== Laser hazard ==== * [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
Line 92: | Line 89: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
==== Weekly ==== * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 99: | Line 101: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 105: | Line 110: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 110: | Line 115: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 134: | Line 140: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/16(Fri.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.
- Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
- Yaw damping stared working by changing polarity.
- Beam alignment to both end and REFL port was confirmed the last night.
- ~10rad shift was seen as usual.
- Clipping was fixed by PSL alignment yesterday.
- PR3 is being shifted to yaw by pump down by ~300urad.
- LSC model as full model started running at k1imc0. Dolhpin will be conected soon.
- Camera: Yokozawa
- IYAC and IXAC areas are being pumped down.
- CRY: Mirror reached at 18K.
Work plan (*:responsible person)
- VAC: Uchiyama
- Pump down.
- DGS: *Miyakawa
- 10GB network card at dc0 will be replaced.
Laser hazard
- [AM] IR: PSL, Green: off.
- [PM] IR: PSL, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools