Differences between revisions 326 and 393 (spanning 67 versions)
Revision 326 as of 2018-03-07 09:19:59
Size: 9286
Comment:
Revision 393 as of 2018-04-18 09:23:48
Size: 11927
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/18(Wed.) ===
Line 54: Line 52:
2017/3/6(Wed.) * Remote participants by eZuce: None
Line 56: Line 54:
 * Remote participants by eZuce: Izumi ==== Report of work (*:responsible person) ====
Line 58: Line 56:
 * Report of work (*:responsible person)  * VAC: *Kimura
  * One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
  * There are 3 ways to the operation in the newt week;
   * Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.
   * Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.
   * Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.
Line 60: Line 63:
  * Alignment: Enomoto, Izumi
   * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.

  * AOS: Akutsu, Michimura
   * We replace all the items which were not compatible to vacuum.

 * Tcam:
  * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.

  * CRY: mirror temperature 24K.

 * Work plan (*:responsible person)

  * Alignment: Enomoto
   * PD at BS will be moved to REFL.
   * Connection of PD signal to DAQ should be implemented this week or next week.
   * GigE camera should be placed at the REFL port eventually.

  * AOS: Akutsu, Michimura
   * Alignment of green light to ETMY will be finished today.

 * Laser hazard:
  * AM: Around PR2 for green, Y-end for IR.
  * PM: Around PR2 for green, upstream SR2-3 line for IR.
 * ETMX: *Hasegawa
  * TF for MM coupling of photo sensor was found.
  * RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
Line 86: Line 68:
 * Weekly
  * week of 3/5
   * 3/5 Exchanging items and cleaning inside the PR2 chamber
   * 3/8 IYC door will be closed.
 * ETMY: *Nakano, Shishido
  * Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.
Line 91: Line 71:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.
 * IFO: *Enomoto, Izumi
  * Trial lock of Michelson did not succeed because of too much motion of ETMY.
Line 95: Line 74:
  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
   * Beam alignment to REFL port.
 * BS: *Eleonora, Izumi
  * We are optimizing diagonalization of L2P filter. Needs more time.

 * DGS: *Yamamoto
  * Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.
Line 101: Line 81:
 * Issues
==== Work plan (*:responsible person) ====

 * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
  * Damping, BS L2P, restoring alignment.

 * VAC: *Kimura
  * Identifies the location of leak.


==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F


==== Weekly ====

 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.

 * week of 4/23
  * Operation

==== Issues ====

  * Large leak was found but it is not identified where it is.
Line 108: Line 123:
==== Weekly meeting ==== === Weekly meeting ===
Line 113: Line 128:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 137: Line 158:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/18(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Kimura
    • One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
    • There are 3 ways to the operation in the newt week;
      • Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.

      • Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.

      • Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.

  • ETMX: *Hasegawa
    • TF for MM coupling of photo sensor was found.
    • RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
  • ETMY: *Nakano, Shishido
    • Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.
  • IFO: *Enomoto, Izumi
    • Trial lock of Michelson did not succeed because of too much motion of ETMY.
  • BS: *Eleonora, Izumi
    • We are optimizing diagonalization of L2P filter. Needs more time.
  • DGS: *Yamamoto
    • Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Identifies the location of leak.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

  • Large leak was found but it is not identified where it is.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)