9286
Comment:
|
11821
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/25(Wed.) === | |
Line 54: | Line 52: |
2017/3/6(Wed.) | * Remote participants by eZuce: None |
Line 56: | Line 54: |
* Remote participants by eZuce: Izumi | ==== Report of work (*:responsible person) ==== |
Line 58: | Line 56: |
* Report of work (*:responsible person) | * IFO: *Izumi, Enomoto, Nakano + many * Michelson lock lasted ~40min with Guardian. * ETMX had some drift. It may cause lock down. |
Line 60: | Line 60: |
* Alignment: Enomoto, Izumi * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26. |
* Modulation frequency was not tuned yet to iMC length. * Measurement of AM conversion can know the matching of mod. freq. to iMC length. |
Line 63: | Line 63: |
* AOS: Akutsu, Michimura * We replace all the items which were not compatible to vacuum. |
* PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser. |
Line 66: | Line 65: |
* Tcam: * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light. |
* BS: *Eleonora, Izumi, Arai * BS IM feed back was engaged. * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control. * Gain of some loops of oplev servo changed stronger. |
Line 69: | Line 70: |
* CRY: mirror temperature 24K. | * CAL: *Yamamoto, Enomoto, Izumi * Optical measumremnt was measured. * Sensitivity is shown in the control room, being calculated from H(t). |
Line 71: | Line 74: |
* Work plan (*:responsible person) | * Injection: *Miyamoto, Yokozawa |
Line 73: | Line 76: |
* Alignment: Enomoto * PD at BS will be moved to REFL. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
* Noise budget: *Michimura, Enomoto |
Line 78: | Line 78: |
* AOS: Akutsu, Michimura * Alignment of green light to ETMY will be finished today. |
* IOO: *Kokeyama, Enomoto * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control. |
Line 81: | Line 81: |
* Laser hazard: * AM: Around PR2 for green, Y-end for IR. * PM: Around PR2 for green, upstream SR2-3 line for IR. |
* ETMX: *Hasegawa, Nakano, Enomoto * ETMX has some drift for 10-20urad. * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto * ETMY need L damping. * Gardian was implemented. |
Line 86: | Line 89: |
* Weekly * week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
==== Work plan (*:responsible person) ==== |
Line 91: | Line 91: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* BS: *Eleonora, Izumi, Arai * Opleve loop gains will change stronger. |
Line 95: | Line 94: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* CAL: *Yamamoto, Enomoto, Izumi * Cal signal will be injected. * IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
Line 101: | Line 101: |
* Issues | ==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/23 * Michelson control. * 4/28 Operation start ==== Issues ==== |
Line 108: | Line 128: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 113: | Line 133: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 137: | Line 163: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/25(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Michelson lock lasted ~40min with Guardian.
- ETMX had some drift. It may cause lock down.
- Modulation frequency was not tuned yet to iMC length.
- Measurement of AM conversion can know the matching of mod. freq. to iMC length.
- PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
- Michelson lock lasted ~40min with Guardian.
- BS: *Eleonora, Izumi, Arai
- BS IM feed back was engaged.
- Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
- Gain of some loops of oplev servo changed stronger.
- BS IM feed back was engaged.
- CAL: *Yamamoto, Enomoto, Izumi
- Optical measumremnt was measured.
- Sensitivity is shown in the control room, being calculated from H(t).
- Injection: *Miyamoto, Yokozawa
- Noise budget: *Michimura, Enomoto
- IOO: *Kokeyama, Enomoto
- MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
- ETMX: *Hasegawa, Nakano, Enomoto
- ETMX has some drift for 10-20urad.
- ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
- ETMY need L damping.
- Gardian was implemented.
Work plan (*:responsible person)
- BS: *Eleonora, Izumi, Arai
- Opleve loop gains will change stronger.
- CAL: *Yamamoto, Enomoto, Izumi
- Cal signal will be injected.
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools