Differences between revisions 327 and 346 (spanning 19 versions)
Revision 327 as of 2018-03-07 09:24:13
Size: 9278
Comment:
Revision 346 as of 2018-03-16 09:26:09
Size: 9750
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/3/6(Wed.) 2017/3/16(Fri.)
Line 56: Line 53:
 * Remote participants by eZuce: Izumi  * Remote participants by eZuce: None
Line 58: Line 55:
=== Report of work (*:responsible person) ===
 * Alignment: Enomoto, Izumi
  * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
==== Report of work (*:responsible person) ====
Line 62: Line 57:
 * AOS: Akutsu, Michimura
  * We replace all the items which were not compatible to vacuum.
 * VAC: *Uchiyama, Kimura, Suzuki
  * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.
Line 65: Line 60:
 * Tcam:
  * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Yaw damping stared working by changing polarity.
  * Beam alignment to both end and REFL port was confirmed the last night.
   * ~10rad shift was seen as usual.
   * Clipping was fixed by PSL alignment yesterday.
   * PR3 is being shifted to yaw by pump down by ~300urad.
  * LSC model as full model started running at k1imc0. Dolhpin will be conected soon.
Line 68: Line 68:
 * CRY: mirror temperature 24K.  * Camera: Yokozawa
  * IYAC and IXAC areas are being pumped down.
Line 70: Line 71:
=== Work plan (*:responsible person) ===
 * Alignment: Enomoto
  * PD at BS will be moved to REFL.
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.

 * AOS: Akutsu, Michimura
  * Alignment of green light to ETMY will be finished today.

=== Laser hazard ===
 * AM: Around PR2 for green, Y-end for IR.
 * PM: Around PR2 for green, upstream SR2-3 line for IR.
 * CRY: Mirror reached at 18K.
Line 84: Line 74:
=== Weekly ===
 * week of 3/5
  * 3/5 Exchanging items and cleaning inside the PR2 chamber
  * 3/8 IYC door will be closed.
Line 89: Line 75:
==== Work plan (*:responsible person) ====

 * VAC: Uchiyama
  * Pump down.

 * DGS: *Miyakawa
  * 10GB network card at dc0 will be replaced.


==== Laser hazard ====
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [night] IR: all, Green: off

==== Weekly ====
Line 100: Line 101:
  * Connection of PD signal to DAQ should be implemented this week or next week.

Line 106: Line 110:
==== Weekly meeting ==== === Weekly meeting ===
Line 111: Line 115:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21
||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 135: Line 140:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/16(Fri.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Uchiyama, Kimura, Suzuki
    • Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.
  • Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
    • Yaw damping stared working by changing polarity.
    • Beam alignment to both end and REFL port was confirmed the last night.
      • ~10rad shift was seen as usual.
      • Clipping was fixed by PSL alignment yesterday.
      • PR3 is being shifted to yaw by pump down by ~300urad.
    • LSC model as full model started running at k1imc0. Dolhpin will be conected soon.
  • Camera: Yokozawa
    • IYAC and IXAC areas are being pumped down.
  • CRY: Mirror reached at 18K.

Work plan (*:responsible person)

  • VAC: Uchiyama
    • Pump down.
  • DGS: *Miyakawa
    • 10GB network card at dc0 will be replaced.

Laser hazard

  • [AM] IR: PSL, Green: off.
  • [PM] IR: PSL, Green: off.
  • [night] IR: all, Green: off

Weekly

  • week of 3/12
    • TMS installation at ETMY.
    • Connecting ducts at the corner area.
  • week of 3/19
    • Vacuum test at at the corner area.
    • TMS alignment using green light at ETMY.
    • Beam alignment to REFL port.
  • Issues
    • Connection of PD signal to DAQ should be implemented this week or next week.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)