9503
Comment:
|
11281
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/17(Tue.) === | |
Line 54: | Line 52: |
2017/3/7(Thur.) * Remote participants by eZuce: Izumi |
* Remote participants by eZuce: None |
Line 59: | Line 55: |
* VAC: *Kimura * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks. |
|
Line 60: | Line 58: |
* Alignment: *Enomoto * PD in the BS chambers was moved to REFL table. * Offset of coil was offloaded into motors upstream. |
* ETMX: *Hasegawa * Damping for yaw woks somehow and RMS is ~0.2urad. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY: :Miyamoto, Shishido * No progress for damping. * ETMY: *Okutomi * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 64: | Line 66: |
* AOS: *Michimura, Yokogawa, Sugimono * Alignment of green light to ETMY was done, and beam was returned to center area. |
* DGS: *Yamamoto * IO chassis of k1ioo was disconnected somehow. |
Line 68: | Line 70: |
* CRY: mirror temperature increase from 24K 25K during night. | |
Line 72: | Line 74: |
* AOS: *Michimura * Alignment of green at the ETMY table will be done today, so beam can be used outside of ETMY chamber around the ETMY area. However no laser hazard is needed at the ETMY area because power is very small. |
* IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. |
Line 75: | Line 77: |
* Tcam: *Inoue, Cory, Binhua * Illuminator or IYA will be implemented this afternoon. |
* VAC: *Kimura * Identifies the location of leak. * VAC: *Inoue * Vacuum gage for wide area will be installed. |
Line 79: | Line 84: |
* Maintenance of PCs will be done tomorrow. DAQ and some RT models will be stopped. | ==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 81: | Line 92: |
==== Laser hazard ==== * [AM] IR: PSL, Green: PR2. * [PM] IR: upstream SR2-3 line, Green: PR2 |
* [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 87: | Line 98: |
* week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
|
Line 91: | Line 99: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 95: | Line 104: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/23 * Operation |
Line 100: | Line 107: |
==== Issues ==== | |
Line 101: | Line 109: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
* Large leak was found but it is not identified where it is. * IO chassis of k1ioo was disconnected somehow. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 117: | Line 125: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 141: | Line 154: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/17(Tue.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
- ETMX: *Hasegawa
- Damping for yaw woks somehow and RMS is ~0.2urad.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY: :Miyamoto, Shishido
- No progress for damping.
- ETMY: *Okutomi
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
- DGS: *Yamamoto
- IO chassis of k1ioo was disconnected somehow.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
- VAC: *Inoue
- Vacuum gage for wide area will be installed.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
- IO chassis of k1ioo was disconnected somehow.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)