Differences between revisions 330 and 402 (spanning 72 versions)
Revision 330 as of 2018-03-08 09:10:24
Size: 9503
Comment:
Revision 402 as of 2018-04-27 09:27:25
Size: 11280
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 27: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 53: Line 39:
=== 2018/4/26(Thur.) ===
Line 54: Line 41:
2017/3/7(Thur.)

 
* Remote participants by eZuce: Izumi
* Remote participants by eZuce: None
Line 60: Line 45:
 * Alignment: *Enomoto
  * PD in the BS chambers was moved to REFL table.
  * Offset of coil was offloaded into motors upstream.
 * IFO: *Izumi, Enomoto + many
  * Michelson lock lasted longer than 2 and half hours!
  * Alignment control from IFO to ETMX was implemented by dithering ETMX.
  * PR3 alignment was implemented by baffle signal.
  * ETMX damping might be a cause of lock lost.
  * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
  * BS oplev is fed back to not only TM but also IM. (Arai)
Line 64: Line 53:
 * AOS: *Michimura, Yokogawa, Sugimono
  * Alignment of green light to ETMY was done, and beam was returned to center area.
 * WAB: *Akutsu
  * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
  * Equilibrium temperature was 21K.
  * Damping became to strong in low temperature.
Line 67: Line 58:
 * Wire of RM was broken on SR3 during tightening clamp.
Line 68: Line 60:
 * CRY: mirror temperature increase from 24K 25K during night.  * CAL: *Yamamoto
  * Line injection is being tested.
  * UGF serve will not be implemented, so change of optical gain is compensated in off line.

 * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened.
 * Operation schedule and emergency contact list is put on the white board in the control room.
Line 72: Line 69:
 * AOS: *Michimura
  * Alignment of green at the ETMY table will be done today, so beam can be used outside of ETMY chamber around the ETMY area. However no laser hazard is needed at the ETMY area because power is very small.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 75: Line 72:
 * Tcam: *Inoue, Cory, Binhua
  * Illuminator or IYA will be implemented this afternoon.
 *
Line 79: Line 75:
 * Maintenance of PCs will be done tomorrow. DAQ and some RT models will be stopped. ==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 81: Line 83:
==== Laser hazard ====
 * [AM] IR: PSL, Green: PR2.
 * [PM] IR: upstream SR2-3 line, Green: PR2
 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 87: Line 89:
 * week of 3/5
  * 3/5 Exchanging items and cleaning inside the PR2 chamber
  * 3/8 IYC door will be closed.
Line 91: Line 90:
 * week of 3/12
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 95: Line 94:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
==== Issues ====
Line 100: Line 96:

 * Issues
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.
  * PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
  * PR3 also had jumps caused by DAC glitches.
Line 117: Line 110:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 141: Line 140:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/26(Thur.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • Michelson lock lasted longer than 2 and half hours!
    • Alignment control from IFO to ETMX was implemented by dithering ETMX.
    • PR3 alignment was implemented by baffle signal.
    • ETMX damping might be a cause of lock lost.
    • ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
    • BS oplev is fed back to not only TM but also IM. (Arai)
  • WAB: *Akutsu
    • Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
    • Equilibrium temperature was 21K.
    • Damping became to strong in low temperature.
  • Wire of RM was broken on SR3 during tightening clamp.
  • CAL: *Yamamoto
    • Line injection is being tested.
    • UGF serve will not be implemented, so change of optical gain is compensated in off line.
  • Operation wiki page is opened.

  • Operation schedule and emergency contact list is put on the white board in the control room.

Work plan (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

  • PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
  • PR3 also had jumps caused by DAC glitches.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)