9561
Comment:
|
10058
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/7(Thur.) | 2017/3/28(Wed.) |
Line 60: | Line 57: |
* Alignment: *Enomoto * PD in the BS chambers was moved to REFL table. * Offset of coil was offloaded into motors upstream. |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today. * First contact will be removed. * BS: *Enomoto * DAC had some glitches with no output (even dac kill and master SW are off). * It will be investigated more. |
Line 64: | Line 64: |
* AOS: *Michimura, Yokogawa, Sugimono * Alignment of green light to ETMY was done, and beam was returned to center area. |
* BRT: Akutsu * Worked well, it means beam spot can be controllable. * Beam shape looks elliptic a bit. |
Line 67: | Line 68: |
* CRY: mirror temperature increase from 24K 25K during night. |
|
Line 72: | Line 71: |
* AOS: *Michimura * Alignment of green at the ETMY table will be done today, so beam can be used outside of ETMY chamber around the ETMY area. However no laser hazard is needed at the ETMY area because power is very small. |
|
Line 75: | Line 72: |
* Tcam: *Inoue, Cory, Binhua * Illuminator or IYA will be implemented this afternoon. |
==== Laser hazard ==== * [AM] * IR: PSL, Pend 1F * Green: PR2 * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== |
Line 79: | Line 87: |
* Maintenance of PCs will be done tomorrow. DAQ and some RT models will be stopped. | * week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 81: | Line 93: |
==== Laser hazard ==== * [AM] IR: PSL and Y-end, Green: PR2. * [PM] IR: upstream SR2-3 line and Y-end, Green: PR2 |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
Line 85: | Line 97: |
==== Weekly ==== * week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/9 |
Line 103: | Line 101: |
* Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
|
Line 118: | Line 113: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 142: | Line 140: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/28(Wed.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today.
- First contact will be removed.
- BS: *Enomoto
- DAC had some glitches with no output (even dac kill and master SW are off).
- It will be investigated more.
- BRT: Akutsu
- Worked well, it means beam spot can be controllable.
- Beam shape looks elliptic a bit.
Work plan (*:responsible person)
Laser hazard
- [AM]
- IR: PSL, Pend 1F
- Green: PR2
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools