Differences between revisions 332 and 375 (spanning 43 versions)
Revision 332 as of 2018-03-08 09:13:20
Size: 9561
Comment:
Revision 375 as of 2018-04-09 09:15:20
Size: 10283
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/9(Mon.) ===
Line 54: Line 52:
2017/3/7(Thur.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce:
Line 59: Line 55:

 * Alignment: *Enomoto
  * PD in the BS chambers was moved to REFL table.
  * Offset of coil was offloaded into motors upstream.

 * AOS: *Michimura, Yokogawa, Sugimono
  * Alignment of green light to ETMY was done, and beam was returned to center area.
 * IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
  * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
  * Connection between k1lsc and k1bs was done.
Line 68: Line 60:
 * CRY: mirror temperature increase from 24K 25K during night.  * DAQ: *Miyakawa
  * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.
Line 71: Line 65:
 * Alignment: Enomoto
  * Alignment to ETMX will be verified Tuesday evening.
Line 72: Line 68:
 * AOS: *Michimura
  * Alignment of green at the ETMY table will be done today, so beam can be used outside of ETMY chamber around the ETMY area. However no laser hazard is needed at the ETMY area because power is very small.

 * Tcam: *Inoue, Cory, Binhua
  * Illuminator or IYA will be implemented this afternoon.


 * Maintenance of PCs will be done tomorrow. DAQ and some RT models will be stopped.
 * Vacuum: Kimura
  * Disassembling outer frames today
  * Closing will be done tomorrow.
  * Installation of Illuminator and viewport are still remaining. It will be done today.
  * Laser will be stopped day time during this week.
Line 82: Line 75:
 * [AM] IR: PSL and Y-end, Green: PR2.
 * [PM] IR: upstream SR2-3 line and Y-end, Green: PR2
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: PSL, Yend 1F
  * Green: off

 * [night]
  * IR: PSL, Yend 1F
  * Green: off
Line 87: Line 88:
 * week of 3/5
  * 3/5 Exchanging items and cleaning inside the PR2 chamber
  * 3/8 IYC door will be closed.
Line 91: Line 89:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.

  * Connecting ducts at the corner area.
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
Line 96: Line 93:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.


 * Issues
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.
==== Issues ====
Line 118: Line 107:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 142: Line 135:
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/9(Mon.)

* Remote participants by eZuce:

Report of work (*:responsible person)

  • IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
    • Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
    • Connection between k1lsc and k1bs was done.
  • DAQ: *Miyakawa
    • Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.

Work plan (*:responsible person)

  • Alignment: Enomoto
    • Alignment to ETMX will be verified Tuesday evening.
  • Vacuum: Kimura
    • Disassembling outer frames today
    • Closing will be done tomorrow.
    • Installation of Illuminator and viewport are still remaining. It will be done today.
    • Laser will be stopped day time during this week.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: PSL, Yend 1F
    • Green: off
  • [night]
    • IR: PSL, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)