Differences between revisions 332 and 394 (spanning 62 versions)
Revision 332 as of 2018-03-08 09:13:20
Size: 9561
Comment:
Revision 394 as of 2018-04-19 09:14:55
Size: 11255
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/19(Thur.) ===
Line 54: Line 52:
2017/3/7(Thur.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce: Miyoki
Line 59: Line 55:
 * Phase 1 operation was postponed to 4/28 start.
Line 60: Line 57:
 * Alignment: *Enomoto
  * PD in the BS chambers was moved to REFL table.
  * Offset of coil was offloaded into motors upstream.
 * VAC: *Kimura
  * Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning.
  * Leak test will be performed on Sunday morning.
Line 64: Line 61:
 * AOS: *Michimura, Yokogawa, Sugimono
  * Alignment of green light to ETMY was done, and beam was returned to center area.
 * ETMX: *Hasegawa
  * Transfer function of TM to BF is being investigated.
Line 67: Line 64:
 * ETMY: *Nakano, Shishido
  * One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch.
  * RMS motion at REFL port is still dominated by ETMY.
Line 68: Line 68:
 * CRY: mirror temperature increase from 24K 25K during night.  * BS: *Eleonora, Izumi
  * We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad
Line 72: Line 74:
 * AOS: *Michimura
  * Alignment of green at the ETMY table will be done today, so beam can be used outside of ETMY chamber around the ETMY area. However no laser hazard is needed at the ETMY area because power is very small.
 * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
  * Damping, BS L2P, restoring alignment.
Line 75: Line 77:
 * Tcam: *Inoue, Cory, Binhua
  * Illuminator or IYA will be implemented this afternoon.
 * VAC: *Kimura
  * To fix large and small leaks.
Line 79: Line 81:
 * Maintenance of PCs will be done tomorrow. DAQ and some RT models will be stopped. ==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 81: Line 89:
==== Laser hazard ====
 * [AM] IR: PSL and Y-end, Green: PR2.
 * [PM] IR: upstream SR2-3 line and Y-end, Green: PR2
 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 87: Line 95:
 * week of 3/5
  * 3/5 Exchanging items and cleaning inside the PR2 chamber
  * 3/8 IYC door will be closed.
Line 91: Line 96:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
 * week of 4/16
  * Michelson control.
  * Leak check, and fix leaks.
Line 96: Line 100:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/23
  * Opening the last gate valve.
  * 4/28 Operation start
Line 101: Line 104:

 * Issues
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.
==== Issues ====
Line 118: Line 117:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 142: Line 147:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/19(Thur.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • Phase 1 operation was postponed to 4/28 start.
  • VAC: *Kimura
    • Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning.
    • Leak test will be performed on Sunday morning.
  • ETMX: *Hasegawa
    • Transfer function of TM to BF is being investigated.
  • ETMY: *Nakano, Shishido
    • One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch.
    • RMS motion at REFL port is still dominated by ETMY.
  • BS: *Eleonora, Izumi
    • We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • To fix large and small leaks.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check, and fix leaks.
  • week of 4/23
    • Opening the last gate valve.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)