Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/8(Fri.) | 2017/3/23(Fri.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: Izumi, Miyoki |
Line 60: | Line 57: |
* Alignment: *Enomoto, Michimura * Tuning of ETMY damping. * PD of transmitted light of ETMY was implemented. * Oplev of are centered. * Yaw of 0.2Hz of ETMY is still moving. RMS is limited by this ~10urad. |
* IFO: *Izumi, Miyamoto, Eleonora * BS had some difficulty to close control loop of Y of oplev. * T of ETMY control loop was closed. * Circuits of baffle PD are being prepared. |
Line 66: | Line 62: |
* CRY: mirror temperature started increasing because of turning one of the cryo pump off. | * AOS: *Akutsu, Yokogawa * Green team succeeded to reach green and IR to ETMY. * BRT alignment is going on yesterday and today. * Oplev is being prepared at EXC. |
Line 68: | Line 67: |
* Tcam: *Inoue, Cory, Binhua * phi800 door of IX will be closed Monday, IY will be closed Tuesday or Wednesday. |
* Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 74: | Line 74: |
==== Laser hazard ==== * [AM] IR: PSL, Green: PR2. * [PM] IR: PSL, Green: PR2. |
* Alignment: *Eleonora, Miyamoto * BS diagonalization * ETMY damping * AOS: *Akutsu, Yokogawa * BRT alignment is going on yesterday and today. * Oplev work at EXC. |
Line 79: | Line 83: |
==== Laser hazard ==== * [AM] * IR: PSL * Green: around PR2 * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
|
Line 80: | Line 96: |
* week of 3/5 * 3/8 IYC door will be closed. * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 89: | Line 98: |
* Vacuum test at at the corner area. | |
Line 91: | Line 99: |
* Beam alignment to REFL port. | * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
Line 93: | Line 103: |
* week of 3/26 * Rough alignment of ETMX is planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 95: | Line 108: |
* Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
|
Line 110: | Line 120: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 134: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/23(Fri.)
- Remote participants by eZuce: Izumi, Miyoki
Report of work (*:responsible person)
- IFO: *Izumi, Miyamoto, Eleonora
- BS had some difficulty to close control loop of Y of oplev.
- T of ETMY control loop was closed.
- Circuits of baffle PD are being prepared.
- AOS: *Akutsu, Yokogawa
- Green team succeeded to reach green and IR to ETMY.
- BRT alignment is going on yesterday and today.
- Oplev is being prepared at EXC.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- Alignment: *Eleonora, Miyamoto
- BS diagonalization
- ETMY damping
- AOS: *Akutsu, Yokogawa
- BRT alignment is going on yesterday and today.
- Oplev work at EXC.
Laser hazard
- [AM]
- IR: PSL
- Green: around PR2
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21~: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX is planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)