Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/5(Thur.) === | |
Line 54: | Line 52: |
2017/3/8(Fri.) * Remote participants by eZuce: Miyoki |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa |
Line 59: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
|
Line 60: | Line 60: |
* Alignment: *Enomoto, Michimura * Tuning of ETMY damping. * PD of transmitted light of ETMY was implemented. * Oplev of are centered. * Yaw of 0.2Hz of ETMY is still moving. RMS is limited by this ~10urad. |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
Line 66: | Line 63: |
* CRY: mirror temperature started increasing because of turning one of the cryo pump off. | * Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. |
Line 68: | Line 67: |
* Tcam: *Inoue, Cory, Binhua * phi800 door of IX will be closed Monday, IY will be closed Tuesday or Wednesday. |
* DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. * Vacuum: *Kimura * Closing door will be performed in the next week. * PCal: no one to report * TMS: no one to report ==== Work plan (*:responsible person) ==== * Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. * ETMY: *Miyamoto * Cover on Oplev will be set this morning. * DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
Line 72: | Line 90: |
==== Work plan (*:responsible person) ==== | ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 74: | Line 98: |
==== Laser hazard ==== * [AM] IR: PSL, Green: PR2. * [PM] IR: PSL, Green: PR2. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 80: | Line 104: |
* week of 3/5 * 3/8 IYC door will be closed. |
|
Line 83: | Line 105: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
Line 88: | Line 110: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
Line 93: | Line 114: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
==== Issues ==== |
Line 110: | Line 128: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 134: | Line 156: |
* Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/5(Thur.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- Alignment: Izumi
- Both light had been confirmed at REFL yesterday morning.
- IR beam was lost at REFL evening, but green was still seen.
- Both IR and green were still seen at Y end.
- ETMX: *Ushiba
- Circuits and connection are still being checked.
- Dolphin: *Yamamoto
- Connected IMC, IOO and BS.
- Error indicator is seen on BS.
- DAQ: *Yamamoto
- Memory will be increased today. SSD might be tested today at k1tw0.
- Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
- k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
- Vacuum: *Kimura
- Closing door will be performed in the next week.
- PCal: no one to report
- TMS: no one to report
Work plan (*:responsible person)
- Alignment: Izumi
- IR will be re-aligned this morning. It requires green off evening.
- ETMY: *Miyamoto
- Cover on Oplev will be set this morning.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)