Comment:
|
11504
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 53: | Line 50: |
=== 2018/4/17(Tue.) === | |
Line 54: | Line 52: |
2017/3/12(Mon.) * Remote participants by eZuce: Miyoki |
* Remote participants by eZuce: None |
Line 59: | Line 55: |
* VAC: *Kimura * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks. |
|
Line 60: | Line 58: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * Tuning of ETMY damping. Yaw of 0.2Hz of ETMY is still moving. RMS is limited by this ~10urad. * ETEY had jump during weekend. * BS has also jump on alignment, but not related duct connection. * Duct connection made some jumps * PR3 had jump 11am on Sunday. * IMMT oplev was not centered before duct connection. |
* ETMX: *Hasegawa * Damping for yaw woks somehow and RMS is ~0.2urad. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY: :Miyamoto, Shishido * No progress for damping. * ETMY: *Okutomi * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 68: | Line 66: |
* CRY: Mirror reached at 18K. | * DGS: *Yamamoto * IO chassis of k1ioo was disconnected somehow. |
Line 73: | Line 74: |
* VAC: Uchiyama * Duct connection * Tcam: * phi800 door of IX will be closed today. * phi800 door of IY will be closed tomorrow or day after tomorrow. |
* IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. * VAC: *Kimura * Identifies the location of leak. * VAC: *Inoue * Vacuum gage for wide area will be installed. |
Line 81: | Line 85: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 86: | Line 98: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 91: | Line 99: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 96: | Line 104: |
* week of 4/23 * Operation |
|
Line 97: | Line 107: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
==== Issues ==== |
Line 101: | Line 109: |
* Large leak was found but it is not identified where it is. * IO chassis of k1ioo was disconnected somehow. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
|
Line 113: | Line 125: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || | ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
Line 137: | Line 155: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/17(Tue.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
- ETMX: *Hasegawa
- Damping for yaw woks somehow and RMS is ~0.2urad.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY: :Miyamoto, Shishido
- No progress for damping.
- ETMY: *Okutomi
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
- DGS: *Yamamoto
- IO chassis of k1ioo was disconnected somehow.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
- VAC: *Inoue
- Vacuum gage for wide area will be installed.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
- IO chassis of k1ioo was disconnected somehow.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)