Line 11: | Line 11: |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/12(Tue.) | 2017/3/30(Fri.) |
Line 60: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * Diagonal of Bottom filter matrix. * Feedforward using accelerometer to IP error point. * Alignnemtn for IFO will be checked every night. * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well. * Oplev is placed but not calibrated. * LVDT of BF seems to be something wrong. It could be satellite box. |
Line 66: | Line 62: |
* Camera: Yokozawa * IX, IY works inside chambers were done. Pump down will be start tomorrow. * Team will start this week. |
* BS: *Enomoto, Enzo * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains. * Hyper threading should be off. |
Line 70: | Line 66: |
* IMMT: Koseyama * had jump but unknown for other SUS. * It is not clear that the duct connection or kicking table. * Oplev will be centered today. |
* BRT: Nagano * TMS was seen and aligned to QPD. |
Line 75: | Line 69: |
* CRY: Mirror reached at 16K. | |
Line 77: | Line 70: |
* | |
Line 80: | Line 74: |
* VAC: Uchiyama * Duct connection, but they will wait for centering of oplev of IMMT. * Tcam: * phi800 door of IX and IY will be closed today. * Pump down will be start tomorrow. |
* ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. |
Line 86: | Line 77: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * MC alignment will be check every night. * Alignnemtn for IFO will be checked every night. |
* CAL: *Yamamoto * CAL model is tested using iMC. |
Line 90: | Line 80: |
* IMMT: Koseyama * Oplev will be centered today. |
* Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
Line 97: | Line 85: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 100: | Line 92: |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
|
Line 102: | Line 97: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 107: | Line 98: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 112: | Line 104: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
|
Line 113: | Line 108: |
* Issues * Request of using light in the night from Alignment and calibration. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
* week of 4/9 * Closing EXC |
Line 118: | Line 111: |
==== Issues ==== * BS: DAC had some glitches but if DAC is off, no glitch was found. |
|
Line 130: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
|
Line 155: | Line 153: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/30(Fri.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
- Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
- Oplev is placed but not calibrated.
- LVDT of BF seems to be something wrong. It could be satellite box.
- BS: *Enomoto, Enzo
- Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
- Hyper threading should be off.
- BRT: Nagano
- TMS was seen and aligned to QPD.
Work plan (*:responsible person)
- ETMX: *Ushiba, Takahashi
- Beam will be aligned more precisely with aligned IR.
- CAL: *Yamamoto
- CAL model is tested using iMC.
- Camera: Yokozawa
- EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches but if DAC is off, no glitch was found.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)