Line 11: Line 11:
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/20(Fri.) ===
Line 54: Line 52:
2017/3/12(Tue.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce: None
Line 59: Line 55:
 * Phase 1 operation was postponed to 4/28 start and 5/6 end.
Line 60: Line 57:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * Diagonal of Bottom filter matrix.
  * Feedforward using accelerometer to IP error point.
  * Alignnemtn for IFO will be checked every night.
  * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night.
 * VAC: *Kimura
  * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
  * Pump down started 15:50 yesterday.
  * Now vacuum gage shows ~30Pa.
Line 66: Line 62:
 * Camera: Yokozawa
  * IX, IY works inside chambers were done. Pump down will be start tomorrow.
  * Team will start this week.
 * VAC: *Inoue, Yokozawa
  * Vacuum monitor is ready! except for Y arm monitor.
Line 70: Line 65:
 * IMMT: Koseyama
  * had jump but unknown for other SUS.
  * It is not clear that the duct connection or kicking table.
  * Oplev will be centered today.
 * ETMX: *Hasegawa
  * 0.07Hz was damped well!
  * Yaw and pitch are < 1urad.
Line 75: Line 69:
 * CRY: Mirror reached at 16K.  * ETMY: *Nakano, Shishido
  * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
  * Possibility of heat link for 1.6Hz still remains.
  * Beam at REFL seemed to be OK.

 * BS: *Eleonora, Izumi
  * Implementation of L2P filter worked well and they are well decoupled now!
  * Global injection point for length control is ready.
Line 80: Line 82:
 * VAC: Uchiyama
  * Duct connection, but they will wait for centering of oplev of IMMT.
 * Tcam:
  * phi800 door of IX and IY will be closed today.
  * Pump down will be start tomorrow.
 * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
  * Damping, BS L2P, restoring alignment.
Line 86: Line 85:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * MC alignment will be check every night.
  * Alignnemtn for IFO will be checked every night.
 * VAC: *Kimura
  * Leak test will be performed and the gate valve will open on weekend if no problem.

 * Camera: *Inoue, Yokozawa
  * Tcam of Y end will be ready today.
Line 91: Line 92:
 * IMMT: Koseyama
  * Oplev will be centered today.
 * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
  * DMG needs some maintenance for DAQ.
Line 97: Line 98:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 102: Line 111:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 107: Line 112:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/16
  * Michelson control.
  * Leak check, and fix leaks.
  * Opening the last gate valve weekend.
Line 112: Line 117:
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 113: Line 121:
 * Issues
  * Request of using light in the night from Alignment and calibration.
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.
==== Issues ====
Line 130: Line 134:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
Line 155: Line 164:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/20(Fri.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • Phase 1 operation was postponed to 4/28 start and 5/6 end.
  • VAC: *Kimura
    • Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
    • Pump down started 15:50 yesterday.
    • Now vacuum gage shows ~30Pa.
  • VAC: *Inoue, Yokozawa
    • Vacuum monitor is ready! except for Y arm monitor.
  • ETMX: *Hasegawa
    • 0.07Hz was damped well!
    • Yaw and pitch are < 1urad.

  • ETMY: *Nakano, Shishido
    • Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
    • Possibility of heat link for 1.6Hz still remains.
    • Beam at REFL seemed to be OK.
  • BS: *Eleonora, Izumi
    • Implementation of L2P filter worked well and they are well decoupled now!
    • Global injection point for length control is ready.

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Leak test will be performed and the gate valve will open on weekend if no problem.
  • Camera: *Inoue, Yokozawa
    • Tcam of Y end will be ready today.
  • We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
    • DMG needs some maintenance for DAQ.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check, and fix leaks.
    • Opening the last gate valve weekend.
  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)