Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/17(Tue.) ===
Line 54: Line 52:
2017/3/12(Tue.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce: None
Line 59: Line 55:
 * VAC: *Kimura
  * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
Line 60: Line 58:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * Diagonal of Bottom filter matrix.
  * Feedforward using accelerometer to IP error point.
  * Alignnemtn for IFO will be checked every night.
  * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night.
 * ETMX: *Hasegawa
  * Damping for yaw woks somehow and RMS is ~0.2urad.
  * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
 * ETMY: :Miyamoto, Shishido
  * No progress for damping.
 * ETMY TF: *Okutomi
  * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
Line 66: Line 66:
 * Camera: Yokozawa
  * IX, IY works inside chambers were done. Pump down will be start tomorrow.
  * Team will start this week.
 * DGS: *Yamamoto
  * IO chassis of k1ioo was disconnected somehow.
Line 70: Line 69:
 * IMMT: Koseyama
  * had jump but unknown for other SUS.
  * It is not clear that the duct connection or kicking table.
  * Oplev will be centered today.
 * VAC: *Inoue
  * Vacuum gage for wide area will be installed.
Line 75: Line 72:
 * CRY: Mirror reached at 16K.
Line 80: Line 76:
 * VAC: Uchiyama
  * Duct connection, but they will wait for centering of oplev of IMMT.
 * Tcam:
  * phi800 door of IX and IY will be closed today.
  * Pump down will be start tomorrow.
 * IFO: Enomoto, Nakano
  * Damping, BS L2P, restoring alignment.
Line 86: Line 79:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * MC alignment will be check every night.
  * Alignnemtn for IFO will be checked every night.


 * IMMT: Koseyama
  * Oplev will be centered today.
 * VAC: *Kimura
  * Identifies the location of leak.
Line 97: Line 84:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 102: Line 97:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 107: Line 98:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 112: Line 103:
 * week of 4/23
  * Operation
Line 113: Line 106:
 * Issues
  * Request of using light in the night from Alignment and calibration.
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.

==== Issues ====
Line 130: Line 118:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
Line 155: Line 147:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/17(Tue.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Kimura
    • Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
  • ETMX: *Hasegawa
    • Damping for yaw woks somehow and RMS is ~0.2urad.
    • A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  • ETMY: :Miyamoto, Shishido
    • No progress for damping.
  • ETMY TF: *Okutomi
    • ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
  • DGS: *Yamamoto
    • IO chassis of k1ioo was disconnected somehow.
  • VAC: *Inoue
    • Vacuum gage for wide area will be installed.

Work plan (*:responsible person)

  • IFO: Enomoto, Nakano
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Identifies the location of leak.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)