Line 51: | Line 51: |
2017/3/12(Tue.) | 2017/3/19(Mon.) |
Line 53: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Kimura |
Line 57: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * Diagonal of Bottom filter matrix. * Feedforward using accelerometer to IP error point. * Alignnemtn for IFO will be checked every night. * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night. |
* VAC: *Uchiyama, Kimura, Suzuki * 4-5 turbo pumps started. * Currently vacuum level is ~1e-4Pa. * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again. * New control boxes for gate valve test were done. * Currently they work at local place, but they will be controlled remotely in the future. * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm. * PR2 assembly frames will be removed soon. * Power cable was connected to the ground at the power panel and made a short to the ground. |
Line 63: | Line 67: |
* Camera: Yokozawa * IX, IY works inside chambers were done. Pump down will be start tomorrow. * Team will start this week. |
|
Line 67: | Line 68: |
* IMMT: Koseyama * had jump but unknown for other SUS. * It is not clear that the duct connection or kicking table. * Oplev will be centered today. * CRY: Mirror reached at 16K. |
|
Line 77: | Line 72: |
* VAC: Uchiyama * Duct connection, but they will wait for centering of oplev of IMMT. * Tcam: * phi800 door of IX and IY will be closed today. * Pump down will be start tomorrow. * Alignment, ETMY: *Enomoto, Miyo, Miyamoto * MC alignment will be check every night. * Alignnemtn for IFO will be checked every night. |
* Alignment, ETMY: *Izumi * All alignment after pump down will be checked. * PR3 yaw had some drift during pump-down. |
Line 88: | Line 77: |
* IMMT: Koseyama * Oplev will be centered today. |
* Cal: * Calibration test using MC is planned on Wednesday. |
Line 91: | Line 80: |
* VAC: Kimura, Sawada * Door will be closed at 3/23. * EX PD will be removed simonteninaously.: *Yokozawa |
|
Line 94: | Line 86: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
Line 99: | Line 91: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 105: | Line 93: |
* Vacuum test at at the corner area. | |
Line 107: | Line 94: |
* Beam alignment to REFL port. | * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. |
Line 109: | Line 97: |
* 3/26 Pcal will start, and all 1st floor of Y-end will be laser hazard area. | |
Line 111: | Line 100: |
* Request of using light in the night from Alignment and calibration. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
|
Line 152: | Line 137: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/19(Mon.)
- Remote participants by eZuce: Kimura
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- 4-5 turbo pumps started.
- Currently vacuum level is ~1e-4Pa.
- Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
- New control boxes for gate valve test were done.
- Currently they work at local place, but they will be controlled remotely in the future.
- Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
- PR2 assembly frames will be removed soon.
- Power cable was connected to the ground at the power panel and made a short to the ground.
- 4-5 turbo pumps started.
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- All alignment after pump down will be checked.
- PR3 yaw had some drift during pump-down.
- Cal:
- Calibration test using MC is planned on Wednesday.
- VAC: Kimura, Sawada
- Door will be closed at 3/23.
- EX PD will be removed simonteninaously.: *Yokozawa
Laser hazard
- [AM] IR: all, Green: off.
- [PM] IR: all, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- 3/26 Pcal will start, and all 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools