9950
Comment:
|
9510
|
Deletions are marked like this. | Additions are marked like this. |
Line 51: | Line 51: |
2017/3/12(Tue.) | 2017/3/20(Tue.) |
Line 57: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * Diagonal of Bottom filter matrix. * Feedforward using accelerometer to IP error point. * Alignnemtn for IFO will be checked every night. * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night. |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. |
Line 63: | Line 60: |
* Camera: Yokozawa * IX, IY works inside chambers were done. Pump down will be start tomorrow. * Team will start this week. |
* Alignment: *Izumi * All alignment to REFL after pump down was verified. |
Line 67: | Line 63: |
* IMMT: Koseyama * had jump but unknown for other SUS. * It is not clear that the duct connection or kicking table. * Oplev will be centered today. |
|
Line 72: | Line 64: |
* CRY: Mirror reached at 16K. | * ETMY: *Miyamoto |
Line 77: | Line 69: |
* VAC: Uchiyama * Duct connection, but they will wait for centering of oplev of IMMT. * Tcam: * phi800 door of IX and IY will be closed today. * Pump down will be start tomorrow. |
* Alignment, ETMY: *Izumi |
Line 83: | Line 71: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * MC alignment will be check every night. * Alignnemtn for IFO will be checked every night. * IMMT: Koseyama * Oplev will be centered today. |
* Cal: * Calibration test using MC is planned tomorrow. |
Line 94: | Line 76: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
Line 99: | Line 81: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 105: | Line 83: |
* Vacuum test at at the corner area. | |
Line 107: | Line 84: |
* Beam alignment to REFL port. | * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
Line 109: | Line 88: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 111: | Line 93: |
* Request of using light in the night from Alignment and calibration. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. |
|
Line 127: | Line 105: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || | |
Line 152: | Line 131: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/20(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- PR2 assembly frames will be removed soon.
- Alignment: *Izumi
- All alignment to REFL after pump down was verified.
- ETMY: *Miyamoto
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- Cal:
- Calibration test using MC is planned tomorrow.
Laser hazard
- [AM] IR: all, Green: off.
- [PM] IR: all, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools