Size: 9950
Comment:
|
Size: 9495
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 51: | Line 51: |
2017/3/12(Tue.) | 2017/3/12(Wed.) |
Line 57: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * Diagonal of Bottom filter matrix. * Feedforward using accelerometer to IP error point. * Alignnemtn for IFO will be checked every night. * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night. |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Alignment to end was checked last. * BS: Top of the BS chamber is opened now for the work of duct connection. |
Line 64: | Line 65: |
* IX, IY works inside chambers were done. Pump down will be start tomorrow. * Team will start this week. |
* IXA camera alignment was done. |
Line 68: | Line 68: |
* had jump but unknown for other SUS. * It is not clear that the duct connection or kicking table. * Oplev will be centered today. |
* Cable was cut, probably by work of duct connection. |
Line 72: | Line 70: |
* CRY: Mirror reached at 16K. | * CRY: Mirror reached at 18K. |
Line 77: | Line 75: |
* Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. |
|
Line 78: | Line 80: |
* Duct connection, but they will wait for centering of oplev of IMMT. * Tcam: * phi800 door of IX and IY will be closed today. * Pump down will be start tomorrow. |
* Duct connection. |
Line 83: | Line 82: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto * MC alignment will be check every night. * Alignnemtn for IFO will be checked every night. |
* Camera: Yokozawa * Both door will be closed today. Pump down will be start today. |
Line 87: | Line 85: |
* IMMT: Koseyama * Oplev will be centered today. |
* AOS: IYC will be closed and start pump-down. |
Line 111: | Line 106: |
* Request of using light in the night from Alignment and calibration. | |
Line 113: | Line 107: |
* GigE camera should be placed at the REFL port eventually. |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/12(Wed.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
- Tuning of ETMY damping is still going on.
- Alignment to end was checked last.
- BS: Top of the BS chamber is opened now for the work of duct connection.
- Camera: Yokozawa
- IXA camera alignment was done.
- IMMT: Kokeyama
- Cable was cut, probably by work of duct connection.
- CRY: Mirror reached at 18K.
Work plan (*:responsible person)
- Alignment: Enomonoto, Izumi
- IMMT coil driver will be checked.
- REFL camera has been placed and will be setup today.
- VAC: Uchiyama
- Duct connection.
- Camera: Yokozawa
- Both door will be closed today. Pump down will be start today.
- AOS: IYC will be closed and start pump-down.
Laser hazard
- [AM] IR: PSL, Green: off.
- [PM] IR: PSL, Green: off.
Weekly
- week of 3/12
- 3/14: meeting for pump-down check
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
KAGRA/Commissioning/DailyWork << < 2025 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | |||
5 | 6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 |
19 | 20 | 21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools