Line 51: Line 51:
2017/3/12(Tue.) 2017/3/15(Thur.)
Line 57: Line 57:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * Diagonal of Bottom filter matrix.
  * Feedforward using accelerometer to IP error point.
  * Alignnemtn for IFO will be checked every night.
  * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night.
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Beam alignment to both end and REFL port was confirmed the last night.
  * Beam is now being drifted to down slowly at PSL by ~100urad.
  * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
  * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
Line 63: Line 64:
 * Camera: Yokozawa
  * IX, IY works inside chambers were done. Pump down will be start tomorrow.
  * Team will start this week.
 * BS: Top of the BS chamber was tightened but no big shift was not found.
Line 67: Line 66:
 * IMMT: Kokeyama
  * had jump but unknown for other SUS.
  * It is not clear that the duct connection or kicking table.
  * Oplev will be centered today.
 * AOS: IYC and IYA started pumping down.
Line 72: Line 68:
 * CRY: Mirror reached at 16K.  * ETMY: *Enomoto
  * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.

 * CRY: Mirror reached at 18K.
Line 77: Line 76:
 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.
Line 78: Line 81:
  * Duct connection, but they will wait for centering of oplev of IMMT.
 * Tcam:
  * phi800 door of IX and IY will be closed today.
  * Pump down will be start tomorrow.
  * Duct connection.
Line 83: Line 83:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * MC alignment will be check every night.
  * Alignnemtn for IFO will be checked every night.
 * Camera: Yokozawa
  * Both door will be closed today. Pump down will be start today.
Line 87: Line 86:

 * IMMT: Koseyama
  * Oplev will be centered today.
 * AOS: IYC will be closed and start pump-down.
Line 96: Line 92:
 * [night] IR: all, Green: off
Line 111: Line 107:
  * Request of using light in the night from Alignment and calibration.
Line 113: Line 108:
  * GigE camera should be placed at the REFL port eventually.
Line 152: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/15(Thur.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
    • Tuning of ETMY damping is still going on.
    • Beam alignment to both end and REFL port was confirmed the last night.
    • Beam is now being drifted to down slowly at PSL by ~100urad.
    • One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
    • When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
  • BS: Top of the BS chamber was tightened but no big shift was not found.
  • AOS: IYC and IYA started pumping down.
  • ETMY: *Enomoto
    • BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.
  • CRY: Mirror reached at 18K.

Work plan (*:responsible person)

  • Alignment: Enomonoto, Izumi
    • IMMT coil driver will be checked.
    • REFL camera has been placed and will be setup today.
  • VAC: Uchiyama
    • Duct connection.
  • Camera: Yokozawa
    • Both door will be closed today. Pump down will be start today.
  • AOS: IYC will be closed and start pump-down.

Laser hazard

  • [AM] IR: PSL, Green: off.
  • [PM] IR: PSL, Green: off.
  • [night] IR: all, Green: off

Weekly

  • week of 3/12
    • 3/14: meeting for pump-down check
    • TMS installation at ETMY.
    • Connecting ducts at the corner area.
  • week of 3/19
    • Vacuum test at at the corner area.
    • TMS alignment using green light at ETMY.
    • Beam alignment to REFL port.
  • Issues
    • Connection of PD signal to DAQ should be implemented this week or next week.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1