Differences between revisions 341 and 371 (spanning 30 versions)
Revision 341 as of 2018-03-13 11:48:27
Size: 9950
Comment:
Revision 371 as of 2018-04-05 12:26:44
Size: 10890
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 50: Line 50:
=== 2018/4/5(Thur.) ===
Line 51: Line 52:
2017/3/12(Tue.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Line 56: Line 55:
 * Alignment: Izumi
  * Both light had been confirmed at REFL yesterday morning.
  * IR beam was lost at REFL evening, but green was still seen.
  * Both IR and green were still seen at Y end.
Line 57: Line 60:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * Diagonal of Bottom filter matrix.
  * Feedforward using accelerometer to IP error point.
  * Alignnemtn for IFO will be checked every night.
  * IMC was aligned last night, but MCi had ~100urad shift. MC alignment will be check every night.
 * ETMX: *Ushiba
  * Circuits and connection are still being checked.
Line 63: Line 63:
 * Camera: Yokozawa
  * IX, IY works inside chambers were done. Pump down will be start tomorrow.
  * Team will start this week.
 * Dolphin: *Yamamoto
  * Connected IMC, IOO and BS.
  * Error indicator is seen on BS.
Line 67: Line 67:
 * IMMT: Kokeyama
  * had jump but unknown for other SUS.
  * It is not clear that the duct connection or kicking table.
  * Oplev will be centered today.
 * DAQ: *Yamamoto
  * Memory will be increased today. SSD might be tested today at k1tw0.
  * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
  * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
Line 72: Line 72:
 * CRY: Mirror reached at 16K.  * Vacuum: *Kimura
  * Closing door will be performed in the next week.
Line 74: Line 75:
 * PCal: no one to report
 
 * TMS: no one to report
Line 76: Line 80:
 * Alignment: Izumi
  * IR will be re-aligned this morning. It requires green off evening.
Line 77: Line 83:
 * VAC: Uchiyama
  * Duct connection, but they will wait for centering of oplev of IMMT.
 * Tcam:
  * phi800 door of IX and IY will be closed today.
  * Pump down will be start tomorrow.
 * ETMY: *Miyamoto
  * Cover on Oplev will be set this morning.
Line 83: Line 86:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto
  * MC alignment will be check every night.
  * Alignnemtn for IFO will be checked every night.


 * IMMT: Koseyama
  * Oplev will be centered today.
 * DAQ: *Miyakawa
  * Memory will be increased today. SSD might be tested today at k1tw0.
Line 94: Line 91:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 99: Line 104:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 104: Line 105:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
  * 4/5 12:30 at fan hut: Meeting before pump down 1
Line 109: Line 110:
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
Line 110: Line 114:
 * Issues
  * Request of using light in the night from Alignment and calibration.
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.
==== Issues ====
Line 127: Line 128:
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
Line 152: Line 156:
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/5(Thur.)

* Remote participants by eZuce: Kimura, Miyoki, Yokozawa

Report of work (*:responsible person)

  • Alignment: Izumi
    • Both light had been confirmed at REFL yesterday morning.
    • IR beam was lost at REFL evening, but green was still seen.
    • Both IR and green were still seen at Y end.
  • ETMX: *Ushiba
    • Circuits and connection are still being checked.
  • Dolphin: *Yamamoto
    • Connected IMC, IOO and BS.
    • Error indicator is seen on BS.
  • DAQ: *Yamamoto
    • Memory will be increased today. SSD might be tested today at k1tw0.
    • Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
    • k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
  • Vacuum: *Kimura
    • Closing door will be performed in the next week.
  • PCal: no one to report
  • TMS: no one to report

Work plan (*:responsible person)

  • Alignment: Izumi
    • IR will be re-aligned this morning. It requires green off evening.
  • ETMY: *Miyamoto
    • Cover on Oplev will be set this morning.
  • DAQ: *Miyakawa
    • Memory will be increased today. SSD might be tested today at k1tw0.

Laser hazard

* [AM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [PM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [night]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

Weekly

  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
    • 4/5 12:30 at fan hut: Meeting before pump down 1
  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)