Differences between revisions 343 and 354 (spanning 11 versions)
Revision 343 as of 2018-03-14 09:25:32
Size: 9495
Comment:
Revision 354 as of 2018-03-22 11:06:17
Size: 10282
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 51: Line 51:
2017/3/12(Wed.) 2017/3/21(Thur.)
Line 53: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura, Miyoki
Line 57: Line 57:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Alignment to end was checked last.
 * IFO: *Izumi, Miyamoto, Eleonora
  * Daily Beam check was confirmed at the REFL port yesterday evening.
  * Measurement of BS sensing and driving matrix and diagonalizarion of them.
   * This method should be automatically performed, but still we needs some work to be done.
  * T of ETMY was checked and improved. We need the same work for L.
  * LSC screen has been updated.
Line 61: Line 64:
 * BS: Top of the BS chamber is opened now for the work of duct connection.   * AOS: *Akutsu, Yokogawa
   * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
Line 64: Line 68:
 * Camera: Yokozawa
  * IXA camera alignment was done.

 * IMMT: Kokeyama
  * Cable was cut, probably by work of duct connection.

 * CRY: Mirror reached at 18K.
 * IMC, CAL: Yokozawa, Yamamoto, Miyamoto
  * IMC Transmitted light is too low. Alignment should be checked.
  * Injection to MCE for calibration was tested.
  
 * VAC: Uchiyama
  * Vacuum level of X arm is degraded.
Line 75: Line 78:
 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.
 * Alignment: *Izumi
  * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
   * Needs power supply for QPD.
Line 79: Line 82:
 * VAC: Uchiyama
  * Duct connection.

 * Camera: Yokozawa
  * Both door will be closed today. Pump down will be start today.

 * AOS: IYC will be closed and start pump-down.
 * AOS: *Akutsu, Yokogawa
  * TMS alignment at ETMY.
  * Cooling will start at 10AM.
Line 89: Line 88:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Line 94: Line 93:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 100: Line 95:
  * Vacuum test at at the corner area.
Line 102: Line 96:
  * Beam alignment to REFL port.   * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa
Line 104: Line 100:
 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 106: Line 105:
  * Connection of PD signal to DAQ should be implemented this week or next week.
Line 120: Line 117:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
Line 145: Line 143:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/21(Thur.)

  • Remote participants by eZuce: Kimura, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • Daily Beam check was confirmed at the REFL port yesterday evening.
    • Measurement of BS sensing and driving matrix and diagonalizarion of them.
      • This method should be automatically performed, but still we needs some work to be done.
    • T of ETMY was checked and improved. We need the same work for L.
    • LSC screen has been updated.
    • AOS: *Akutsu, Yokogawa
      • Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
  • IMC, CAL: Yokozawa, Yamamoto, Miyamoto
    • IMC Transmitted light is too low. Alignment should be checked.
    • Injection to MCE for calibration was tested.
  • VAC: Uchiyama
    • Vacuum level of X arm is degraded.

Work plan (*:responsible person)

  • Alignment: *Izumi
    • ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
      • Needs power supply for QPD.
  • AOS: *Akutsu, Yokogawa
    • TMS alignment at ETMY.
    • Cooling will start at 10AM.

Laser hazard

  • [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members