Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 51: | Line 51: |
2017/3/15(Thur.) | 2017/3/20(Tue.) |
Line 57: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. |
Line 64: | Line 60: |
* BS: Top of the BS chamber was tightened but no big shift was not found. | * Alignment: *Izumi * All alignment to REFL after pump down was verified. * Only ETMY was off position by ~100urad. |
Line 66: | Line 64: |
* AOS: IYC and IYA started pumping down. | * ETMY: *Miyamoto * Diagonal of sensors. Still going on. |
Line 68: | Line 67: |
* ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. |
* BS: Eleonora, Izumi * Coil balance is going on. |
Line 71: | Line 70: |
* CRY: Mirror reached at 18K. | * IMC: * "sleep" commands were removed from Guardian. * Cal: Yokozawa * We checked all the IMC TFs. |
Line 76: | Line 80: |
* Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. |
* Alignment, ETMY: *Izumi |
Line 80: | Line 82: |
* VAC: Uchiyama * Duct connection. * Camera: Yokozawa * Both door will be closed today. Pump down will be start today. * AOS: IYC will be closed and start pump-down. |
* Cal: Yokozawa * Injection will be tested soon. |
Line 90: | Line 87: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
* [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
Line 95: | Line 92: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 101: | Line 94: |
* Vacuum test at at the corner area. | |
Line 103: | Line 95: |
* Beam alignment to REFL port. | * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
Line 105: | Line 99: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 107: | Line 104: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 121: | Line 116: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/20(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- PR2 assembly frames will be removed soon.
- Alignment: *Izumi
- All alignment to REFL after pump down was verified.
- Only ETMY was off position by ~100urad.
- All alignment to REFL after pump down was verified.
- ETMY: *Miyamoto
- Diagonal of sensors. Still going on.
- BS: Eleonora, Izumi
- Coil balance is going on.
- IMC:
- "sleep" commands were removed from Guardian.
- Cal: Yokozawa
- We checked all the IMC TFs.
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- Cal: Yokozawa
- Injection will be tested soon.
Laser hazard
- [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools