Differences between revisions 345 and 359 (spanning 14 versions)
Revision 345 as of 2018-03-15 09:32:12
Size: 10012
Comment:
Revision 359 as of 2018-03-27 09:20:03
Size: 10223
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 51: Line 51:
2017/3/15(Thur.) 2017/3/27(Tue.)
Line 53: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Yokozawa
Line 57: Line 57:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Beam alignment to both end and REFL port was confirmed the last night.
  * Beam is now being drifted to down slowly at PSL by ~100urad.
  * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
  * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
 * Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
  * All are free except for Pre-isolator.
  * Cable connections seemed to be fine.
  * First contact will be removed.
Line 64: Line 62:
 * BS: Top of the BS chamber was tightened but no big shift was not found.  * Oplev at ETMX: Akutsu
  * Preparation is almost done.
Line 66: Line 65:
 * AOS: IYC and IYA started pumping down.

 * ETMY: *Enomoto
  * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.

 * CRY: Mirror reached at 18K.
 * BS: *Enomoto
  * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.
Line 76: Line 71:
 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.
 * Camera: *Inoue, Yokozawa
  * ETMX PD will be removed.
  * GigE camera will be removed today and placed next week.
Line 80: Line 75:
 * VAC: Uchiyama
  * Duct connection.
 * Oplev at ETMX: *Akutsu, Simon
  * Once first contact is removed, opelev will be aligned.
Line 83: Line 78:
 * Camera: Yokozawa
  * Both door will be closed today. Pump down will be start today.
 * BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
  * Alignment
Line 86: Line 81:
 * AOS: IYC will be closed and start pump-down. ==== Laser hazard ====
 * [AM]
  * IR: PSL
  * Green: PR2
 * [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

==== Weekly ====
Line 89: Line 96:
==== Laser hazard ====
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [night] IR: all, Green: off
 * week of 3/26
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa
Line 94: Line 102:
==== Weekly ====
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
Line 100: Line 106:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/9
Line 107: Line 110:
  * Connection of PD signal to DAQ should be implemented this week or next week.
Line 121: Line 122:
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/27(Tue.)

  • Remote participants by eZuce: Yokozawa

Report of work (*:responsible person)

  • Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
    • All are free except for Pre-isolator.
    • Cable connections seemed to be fine.
    • First contact will be removed.
  • Oplev at ETMX: Akutsu
    • Preparation is almost done.
  • BS: *Enomoto
    • Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.

Work plan (*:responsible person)

  • Camera: *Inoue, Yokozawa
    • ETMX PD will be removed.
    • GigE camera will be removed today and placed next week.
  • Oplev at ETMX: *Akutsu, Simon
    • Once first contact is removed, opelev will be aligned.
  • BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
    • Alignment

Laser hazard

  • [AM]
    • IR: PSL
    • Green: PR2
  • [PM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 3/26
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • 3/27 EX PD will be removed.: *Yokozawa
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)