2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 51: | Line 51: |
2017/3/15(Thur.) | 2017/3/30(Fri.) |
Line 57: | Line 57: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well. * Oplev is placed but not calibrated. * LVDT of BF seems to be something wrong. It could be satellite box. |
Line 64: | Line 62: |
* BS: Top of the BS chamber was tightened but no big shift was not found. | * BS: *Enomoto, Enzo * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains. * Hyper threading should be off. |
Line 66: | Line 66: |
* AOS: IYC and IYA started pumping down. | * BRT: Nagano * TMS was seen and aligned to QPD. |
Line 68: | Line 69: |
* ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. |
|
Line 71: | Line 70: |
* CRY: Mirror reached at 18K. |
* |
Line 76: | Line 74: |
* Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. |
* ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. |
Line 80: | Line 77: |
* VAC: Uchiyama * Duct connection. |
* CAL: *Yamamoto * CAL model is tested using iMC. |
Line 84: | Line 81: |
* Both door will be closed today. Pump down will be start today. * AOS: IYC will be closed and start pump-down. |
* EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
Line 90: | Line 85: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 95: | Line 97: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 100: | Line 98: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 105: | Line 104: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
|
Line 106: | Line 108: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. |
* week of 4/9 * Closing EXC |
Line 109: | Line 111: |
==== Issues ==== * BS: DAC had some glitches but if DAC is off, no glitch was found. |
|
Line 121: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/30(Fri.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
- Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
- Oplev is placed but not calibrated.
- LVDT of BF seems to be something wrong. It could be satellite box.
- BS: *Enomoto, Enzo
- Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
- Hyper threading should be off.
- BRT: Nagano
- TMS was seen and aligned to QPD.
Work plan (*:responsible person)
- ETMX: *Ushiba, Takahashi
- Beam will be aligned more precisely with aligned IR.
- CAL: *Yamamoto
- CAL model is tested using iMC.
- Camera: Yokozawa
- EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches but if DAC is off, no glitch was found.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools