Differences between revisions 345 and 390 (spanning 45 versions)
Revision 345 as of 2018-03-15 09:32:12
Size: 10012
Comment:
Revision 390 as of 2018-04-17 09:17:36
Size: 11281
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 50: Line 50:
=== 2018/4/17(Tue.) ===
Line 51: Line 52:
2017/3/15(Thur.)

 
* Remote participants by eZuce: None
* Remote participants by eZuce: None
Line 56: Line 55:
 * VAC: *Kimura
  * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
Line 57: Line 58:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Beam alignment to both end and REFL port was confirmed the last night.
  * Beam is now being drifted to down slowly at PSL by ~100urad.
  * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
  * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
 * ETMX: *Hasegawa
  * Damping for yaw woks somehow and RMS is ~0.2urad.
  * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
 * ETMY: :Miyamoto, Shishido
  * No progress for damping.
 * ETMY: *Okutomi
  * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
Line 64: Line 66:
 * BS: Top of the BS chamber was tightened but no big shift was not found.  * DGS: *Yamamoto
  * IO chassis of k1ioo was disconnected somehow.
Line 66: Line 69:
 * AOS: IYC and IYA started pumping down.
Line 68: Line 70:
 * ETMY: *Enomoto
  * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.

 * CRY: Mirror reached at 18K.
Line 76: Line 74:
 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.
 * IFO: Enomoto, Nakano
  * Damping, BS L2P, restoring alignment.
Line 80: Line 77:
 * VAC: Uchiyama
  * Duct connection.
 * VAC: *Kimura
  * Identifies the location of leak.
Line 83: Line 80:
 * Camera: Yokozawa
  * Both door will be closed today. Pump down will be start today.

 * AOS: IYC will be closed and start pump-down.
 * VAC: *Inoue
  * Vacuum gage for wide area will be installed.
Line 90: Line 85:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [night] IR: all, Green: off
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 95: Line 98:
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 100: Line 99:
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 105: Line 104:
 * week of 4/23
  * Operation
Line 106: Line 107:
 * Issues
  * Connection of PD signal to DAQ should be implemented this week or next week.
==== Issues ====
Line 109: Line 109:
  * Large leak was found but it is not identified where it is.
  * IO chassis of k1ioo was disconnected somehow.
  * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
Line 121: Line 125:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
Line 146: Line 154:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/17(Tue.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Kimura
    • Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
  • ETMX: *Hasegawa
    • Damping for yaw woks somehow and RMS is ~0.2urad.
    • A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  • ETMY: :Miyamoto, Shishido
    • No progress for damping.
  • ETMY: *Okutomi
    • ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
  • DGS: *Yamamoto
    • IO chassis of k1ioo was disconnected somehow.

Work plan (*:responsible person)

  • IFO: Enomoto, Nakano
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Identifies the location of leak.
  • VAC: *Inoue
    • Vacuum gage for wide area will be installed.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

  • Large leak was found but it is not identified where it is.
  • IO chassis of k1ioo was disconnected somehow.
  • A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  • ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)