10012
Comment:
|
11281
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/17(Tue.) === | |
Line 51: | Line 52: |
2017/3/15(Thur.) * Remote participants by eZuce: None |
* Remote participants by eZuce: None |
Line 56: | Line 55: |
* VAC: *Kimura * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks. |
|
Line 57: | Line 58: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. |
* ETMX: *Hasegawa * Damping for yaw woks somehow and RMS is ~0.2urad. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY: :Miyamoto, Shishido * No progress for damping. * ETMY: *Okutomi * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 64: | Line 66: |
* BS: Top of the BS chamber was tightened but no big shift was not found. | * DGS: *Yamamoto * IO chassis of k1ioo was disconnected somehow. |
Line 66: | Line 69: |
* AOS: IYC and IYA started pumping down. | |
Line 68: | Line 70: |
* ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. * CRY: Mirror reached at 18K. |
|
Line 76: | Line 74: |
* Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. |
* IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. |
Line 80: | Line 77: |
* VAC: Uchiyama * Duct connection. |
* VAC: *Kimura * Identifies the location of leak. |
Line 83: | Line 80: |
* Camera: Yokozawa * Both door will be closed today. Pump down will be start today. * AOS: IYC will be closed and start pump-down. |
* VAC: *Inoue * Vacuum gage for wide area will be installed. |
Line 90: | Line 85: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 95: | Line 98: |
* week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 100: | Line 99: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 105: | Line 104: |
* week of 4/23 * Operation |
|
Line 106: | Line 107: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. |
==== Issues ==== |
Line 109: | Line 109: |
* Large leak was found but it is not identified where it is. * IO chassis of k1ioo was disconnected somehow. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
|
Line 121: | Line 125: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
|
Line 146: | Line 154: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/17(Tue.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
- ETMX: *Hasegawa
- Damping for yaw woks somehow and RMS is ~0.2urad.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY: :Miyamoto, Shishido
- No progress for damping.
- ETMY: *Okutomi
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
- DGS: *Yamamoto
- IO chassis of k1ioo was disconnected somehow.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
- VAC: *Inoue
- Vacuum gage for wide area will be installed.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
- IO chassis of k1ioo was disconnected somehow.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools