Differences between revisions 346 and 347
Revision 346 as of 2018-03-16 09:26:09
Size: 9750
Comment:
Revision 347 as of 2018-03-19 09:32:18
Size: 9838
Comment:
Deletions are marked like this. Additions are marked like this.
Line 51: Line 51:
2017/3/16(Fri.) 2017/3/19(Mon.)
Line 53: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura
Line 58: Line 58:
  * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.   * 4-5 turbo pumps started.
   * Currently vacuum level is ~1e-4Pa.
   * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
  * New control boxes for gate valve test were done.
   * Currently they work at local place, but they will be controlled remotely in the future.
  * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
  * PR2 assembly frames will be removed soon.
  * Power cable was connected to the ground at the power panel and made a short to the ground.
Line 60: Line 67:
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Yaw damping stared working by changing polarity.
  * Beam alignment to both end and REFL port was confirmed the last night.
   * ~10rad shift was seen as usual.
   * Clipping was fixed by PSL alignment yesterday.
   * PR3 is being shifted to yaw by pump down by ~300urad.
  * LSC model as full model started running at k1imc0. Dolhpin will be conected soon.

 * Camera: Yokozawa
  * IYAC and IXAC areas are being pumped down.

 * CRY: Mirror reached at 18K.
Line 77: Line 72:
 * VAC: Uchiyama
  * Pump down.
 * Alignment, ETMY: *Izumi
  * All alignment after pump down will be checked.
  * PR3 yaw had some drift during pump-down.
Line 80: Line 76:
 * DGS: *Miyakawa
  * 10GB network card at dc0 will be replaced.

 * Cal:
  * Calibration test using MC is planned on Wednesday.

 * VAC: Kimura, Sawada
  * Door will be closed at 3/23.
  * EX PD will be removed simonteninaously.: *Yokozawa
Line 85: Line 86:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [AM] IR: all, Green: off.
 * [PM] IR: all, Green: off.
Line 90: Line 91:
 * week of 3/12
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 95: Line 93:
  * Vacuum test at at the corner area.
Line 97: Line 94:
  * Beam alignment to REFL port.   * 3/21: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
Line 99: Line 97:
 * 3/26 Pcal will start, and all 1st floor of Y-end will be laser hazard area.
Line 101: Line 100:
  * Connection of PD signal to DAQ should be implemented this week or next week.

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/19(Mon.)

  • Remote participants by eZuce: Kimura

Report of work (*:responsible person)

  • VAC: *Uchiyama, Kimura, Suzuki
    • 4-5 turbo pumps started.
      • Currently vacuum level is ~1e-4Pa.
      • Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
    • New control boxes for gate valve test were done.
      • Currently they work at local place, but they will be controlled remotely in the future.
    • Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
    • PR2 assembly frames will be removed soon.
    • Power cable was connected to the ground at the power panel and made a short to the ground.

Work plan (*:responsible person)

  • Alignment, ETMY: *Izumi
    • All alignment after pump down will be checked.
    • PR3 yaw had some drift during pump-down.
  • Cal:
    • Calibration test using MC is planned on Wednesday.
  • VAC: Kimura, Sawada
    • Door will be closed at 3/23.
    • EX PD will be removed simonteninaously.: *Yokozawa

Laser hazard

  • [AM] IR: all, Green: off.
  • [PM] IR: all, Green: off.
  • [night] IR: all, Green: off

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
  • 3/26 Pcal will start, and all 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 4 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30          


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)