Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 51: | Line 51: |
2017/3/16(Fri.) | 2017/3/21(Thur.) |
Line 53: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Kimura, Miyoki |
Line 57: | Line 57: |
* VAC: *Uchiyama, Kimura, Suzuki * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today. |
* IFO: *Izumi, Miyamoto, Eleonora * Daily Beam check was confirmed at the REFL port yesterday evening. * Measurement of BS sensing and driving matrix and diagonalizarion of them. * This method should be automatically performed, but still we needs some work to be done. * T of ETMY was checked and improved. We need the same work for L. * LSC screen has been updated. |
Line 60: | Line 64: |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Yaw damping stared working by changing polarity. * Beam alignment to both end and REFL port was confirmed the last night. * ~10rad shift was seen as usual. * Clipping was fixed by PSL alignment yesterday. * PR3 is being shifted to yaw by pump down by ~300urad. * LSC model as full model started running at k1imc0. Dolhpin will be conected soon. |
* AOS: *Akutsu, Yokogawa * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order. |
Line 68: | Line 67: |
* Camera: Yokozawa * IYAC and IXAC areas are being pumped down. |
|
Line 71: | Line 68: |
* CRY: Mirror reached at 18K. |
* IMC, CAL: Yokozawa, Yamamoto, Miyamoto * IMC Transmitted light is too low. Alignment should be checked. * Injection to MCE for calibration was tested. * VAC: Uchiyama * Vacuum level of X arm is degraded. |
Line 77: | Line 78: |
* VAC: Uchiyama * Pump down. |
* Alignment: *Izumi * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX. * Needs power supply for QPD. |
Line 80: | Line 82: |
* DGS: *Miyakawa * 10GB network card at dc0 will be replaced. |
* AOS: *Akutsu, Yokogawa * TMS alignment at ETMY. * Cooling will start at 10AM. |
Line 85: | Line 88: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
* [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
Line 90: | Line 93: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 95: | Line 95: |
* Vacuum test at at the corner area. | |
Line 97: | Line 96: |
* Beam alignment to REFL port. | * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
Line 99: | Line 100: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 101: | Line 105: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 115: | Line 117: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/21(Thur.)
- Remote participants by eZuce: Kimura, Miyoki
Report of work (*:responsible person)
- IFO: *Izumi, Miyamoto, Eleonora
- Daily Beam check was confirmed at the REFL port yesterday evening.
- Measurement of BS sensing and driving matrix and diagonalizarion of them.
- This method should be automatically performed, but still we needs some work to be done.
- T of ETMY was checked and improved. We need the same work for L.
- LSC screen has been updated.
- AOS: *Akutsu, Yokogawa
- Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
- IMC, CAL: Yokozawa, Yamamoto, Miyamoto
- IMC Transmitted light is too low. Alignment should be checked.
- Injection to MCE for calibration was tested.
- VAC: Uchiyama
- Vacuum level of X arm is degraded.
Work plan (*:responsible person)
- Alignment: *Izumi
- ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
- Needs power supply for QPD.
- ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
- AOS: *Akutsu, Yokogawa
- TMS alignment at ETMY.
- Cooling will start at 10AM.
Laser hazard
- [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
- [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
- [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21~: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)