Differences between revisions 346 and 365 (spanning 19 versions)
Revision 346 as of 2018-03-16 09:26:09
Size: 9750
Comment:
Revision 365 as of 2018-04-02 10:45:36
Size: 11728
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 50: Line 50:

2017/3/16(Fri.)
2018/4/2(Fri.)

* Remote participants by eZuce: Enomoto

==== Report of work (*:responsible person) ====
* ETMX: *Ushiba
 * Confirmed the returned beam at REFL
 * Calibration of OpLev is on going (mostly finished)
 * Start Characterization

* ETMY: *Miyamoto
  * Damping is working well. Less than 2urad RMS.

* BS: *Enomoto
 * Two different problems identified
  * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
  * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero

* PCal: Binhua
 * Aligned the beam within the PCal module
 
* ETMX camera: Yokozawa
 * Ready but not installed

* TMS: no one to report

==== Work plan (*:responsible person) ====

* ETMX: *Ushiba, Miyamoto
  * Start Characterization

* BS: Enomoto
 * Check the glitches over the weekend

* PCal: Binhua
  * Measure PCal transfer functions

* ETMX Camera: Yokozawa
  * Set up necessary components to take high frame rate pictures

==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F


2017/3/30(Fri.)
Line 57: Line 109:
 * VAC: *Uchiyama, Kimura, Suzuki
  * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.

 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Yaw damping stared working by changing polarity.
  * Beam alignment to both end and REFL port was confirmed the last night.
   * ~10rad shift was seen as usual.
   * Clipping was fixed by PSL alignment yesterday.
   * PR3 is being shifted to yaw by pump down by ~300urad.
  * LSC model as full model started running at k1imc0. Dolhpin will be conected soon.
 * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
  * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
  * Oplev is placed but not calibrated.
  * LVDT of BF seems to be something wrong. It could be satellite box.

 * BS: *Enomoto, Enzo
  * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
  * Hyper threading should be off.

 * BRT: Nagano
  * TMS was seen and aligned to QPD.


 *

==== Work plan (*:responsible person) ====

 * ETMX: *Ushiba, Takahashi
  * Beam will be aligned more precisely with aligned IR.

 * CAL: *Yamamoto
  * CAL model is tested using iMC.
Line 69: Line 133:
  * IYAC and IXAC areas are being pumped down.

 * CRY: Mirror reached at 18K.



==== Work plan (*:responsible person) ====

 * VAC: Uchiyama
  * Pump down.

 * DGS: *Miyakawa
  * 10GB network card at dc0 will be replaced.
  * EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Line 85: Line 137:
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [night] IR: all, Green: off
 * [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 90: Line 149:
 * week of 3/12
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.

 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.


 * Issues
  * Connection of PD signal to DAQ should be implemented this week or next week.

 * week of 3/26
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa

 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.

 * week of 4/9
  * Closing EXC

==== Issues ====

 * BS: DAC had some glitches but if DAC is off, no glitch was found.
Line 115: Line 178:
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/2(Fri.)

* Remote participants by eZuce: Enomoto

Report of work (*:responsible person)

* ETMX: *Ushiba

  • Confirmed the returned beam at REFL
  • Calibration of OpLev is on going (mostly finished)

  • Start Characterization

* ETMY: *Miyamoto

  • Damping is working well. Less than 2urad RMS.

* BS: *Enomoto

  • Two different problems identified
    • Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone

    • Glitches -> Looks like the same problem as ETMY: DAC output goes to zero

* PCal: Binhua

  • Aligned the beam within the PCal module

* ETMX camera: Yokozawa

  • Ready but not installed

* TMS: no one to report

Work plan (*:responsible person)

* ETMX: *Ushiba, Miyamoto

  • Start Characterization

* BS: Enomoto

  • Check the glitches over the weekend

* PCal: Binhua

  • Measure PCal transfer functions

* ETMX Camera: Yokozawa

  • Set up necessary components to take high frame rate pictures

Laser hazard

* [AM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [PM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [night]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

2017/3/30(Fri.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
    • Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
    • Oplev is placed but not calibrated.
    • LVDT of BF seems to be something wrong. It could be satellite box.
  • BS: *Enomoto, Enzo
    • Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
    • Hyper threading should be off.
  • BRT: Nagano
    • TMS was seen and aligned to QPD.

Work plan (*:responsible person)

  • ETMX: *Ushiba, Takahashi
    • Beam will be aligned more precisely with aligned IR.
  • CAL: *Yamamoto
    • CAL model is tested using iMC.
  • Camera: Yokozawa
    • EX camera takes every one hour. It is necessary 1 sec picture in the weekend.

Laser hazard

  • [AM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 3/26
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • 3/27 EX PD will be removed.: *Yokozawa
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
    • Closing EXC

Issues

  • BS: DAC had some glitches but if DAC is off, no glitch was found.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1