Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/13(Fri.) === | |
Line 51: | Line 52: |
2017/3/16(Fri.) * Remote participants by eZuce: None |
* Remote participants by eZuce: Miyoki |
Line 56: | Line 55: |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw. * Centering of oplev was done this morning * Alignment was tuned IMC from 0.3/1.0->0.7/1.0 * ETMY damping was improved a bit by Nakano. Now ~3urad. |
|
Line 57: | Line 61: |
* VAC: *Uchiyama, Kimura, Suzuki * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today. * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Yaw damping stared working by changing polarity. * Beam alignment to both end and REFL port was confirmed the last night. * ~10rad shift was seen as usual. * Clipping was fixed by PSL alignment yesterday. * PR3 is being shifted to yaw by pump down by ~300urad. * LSC model as full model started running at k1imc0. Dolhpin will be conected soon. * Camera: Yokozawa * IYAC and IXAC areas are being pumped down. * CRY: Mirror reached at 18K. |
* VAC: *Kimura * View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. |
Line 76: | Line 67: |
* IFO: *Enomoto, Nakano, Nagano * Alignment of REFL port aftenoon. * Some damping work. |
|
Line 77: | Line 71: |
* VAC: Uchiyama * Pump down. * DGS: *Miyakawa * 10GB network card at dc0 will be replaced. |
* VAC: *Kimura * Pumping down will start ~10am today. |
Line 85: | Line 76: |
* [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: Upstream SR2-3 line, Yend 1F * Green: off * [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 90: | Line 89: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
|
Line 94: | Line 90: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. |
Line 99: | Line 96: |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
|
Line 100: | Line 101: |
* Issues * Connection of PD signal to DAQ should be implemented this week or next week. |
* week of 4/23 * Operation |
Line 103: | Line 104: |
==== Issues ==== | |
Line 115: | Line 116: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
|
Line 140: | Line 145: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/13(Fri.)
* Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
- Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
- Centering of oplev was done this morning
Alignment was tuned IMC from 0.3/1.0->0.7/1.0
- ETMY damping was improved a bit by Nakano. Now ~3urad.
- VAC: *Kimura
- View port for oplev at ETMX was attached yesterday's afternoon.
- All the preparation was done and the door of EXC was closed.
Work plan (*:responsible person)
- IFO: *Enomoto, Nakano, Nagano
- Alignment of REFL port aftenoon.
- Some damping work.
- VAC: *Kimura
- Pumping down will start ~10am today.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2.
- Closing EXC.
- Some controls for Michelson.
- 4/13 morning: Pump down starts.
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)