Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 51: | Line 51: |
2017/3/19(Mon.) | 2017/3/28(Wed.) |
Line 53: | Line 53: |
* Remote participants by eZuce: Kimura | * Remote participants by eZuce: None |
Line 57: | Line 57: |
* VAC: *Uchiyama, Kimura, Suzuki * 4-5 turbo pumps started. * Currently vacuum level is ~1e-4Pa. * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again. * New control boxes for gate valve test were done. * Currently they work at local place, but they will be controlled remotely in the future. * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm. * PR2 assembly frames will be removed soon. * Power cable was connected to the ground at the power panel and made a short to the ground. |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today. * First contact will be removed. * BS: *Enomoto * DAC had some glitches with no output (even dac kill and master SW are off). * It will be investigated more. |
Line 67: | Line 64: |
* BRT: Akutsu * Alignment was done and BRT worked well, it means that the beam position can be controlled after BRT. * Beam shape looks elliptic a bit. |
|
Line 72: | Line 71: |
* Alignment, ETMY: *Izumi * All alignment after pump down will be checked. * PR3 yaw had some drift during pump-down. * Cal: * Calibration test using MC is planned on Wednesday. * VAC: Kimura, Sawada * Door will be closed at 3/23. * EX PD will be removed simonteninaously.: *Yokozawa |
|
Line 86: | Line 73: |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: PSL, Pend 1F * Green: PR2 * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 92: | Line 86: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. |
|
Line 98: | Line 88: |
* Rough alignment of ETMX will be planed using IR. | |
Line 100: | Line 89: |
* Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
|
Line 102: | Line 101: |
* ETMX Type A: GAS filter had a sudden jump, and it is being fixed today. * BS: DAC had some glitches with no output (even dac kill and master SW are off). |
|
Line 114: | Line 116: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/28(Wed.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today.
- First contact will be removed.
- BS: *Enomoto
- DAC had some glitches with no output (even dac kill and master SW are off).
- It will be investigated more.
- BRT: Akutsu
- Alignment was done and BRT worked well, it means that the beam position can be controlled after BRT.
- Beam shape looks elliptic a bit.
Work plan (*:responsible person)
Laser hazard
- [AM]
- IR: PSL, Pend 1F
- Green: PR2
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
- ETMX Type A: GAS filter had a sudden jump, and it is being fixed today.
- BS: DAC had some glitches with no output (even dac kill and master SW are off).
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)