Differences between revisions 349 and 359 (spanning 10 versions)
Revision 349 as of 2018-03-19 09:35:23
Size: 10137
Comment:
Revision 359 as of 2018-03-27 09:20:03
Size: 10223
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 51: Line 51:
2017/3/19(Mon.) 2017/3/27(Tue.)
Line 53: Line 53:
 * Remote participants by eZuce: Kimura  * Remote participants by eZuce: Yokozawa
Line 57: Line 57:
 * VAC: *Uchiyama, Kimura, Suzuki
  * 4-5 turbo pumps started.
   * Currently vacuum level is ~1e-4Pa.
   * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again.
  * New control boxes for gate valve test were done.
   * Currently they work at local place, but they will be controlled remotely in the future.
  * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm.
  * PR2 assembly frames will be removed soon.
  * Power cable was connected to the ground at the power panel and made a short to the ground.
 * Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
  * All are free except for Pre-isolator.
  * Cable connections seemed to be fine.
  * First contact will be removed.
Line 67: Line 62:
 * Oplev at ETMX: Akutsu
  * Preparation is almost done.
Line 68: Line 65:
 * BS: *Enomoto
  * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.
Line 72: Line 71:
 * Alignment, ETMY: *Izumi
  * All alignment after pump down will be checked.
  * PR3 yaw had some drift during pump-down.
 * Camera: *Inoue, Yokozawa
  * ETMX PD will be removed.
  * GigE camera will be removed today and placed next week.
Line 76: Line 75:
 * Oplev at ETMX: *Akutsu, Simon
  * Once first contact is removed, opelev will be aligned.
Line 77: Line 78:
 * Cal:
  * Calibration test using MC is planned on Wednesday.

 * VAC: Kimura, Sawada
  * Door will be closed at 3/23.
  * EX PD will be removed simonteninaously.: *Yokozawa
 * BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
  * Alignment
Line 86: Line 82:
 * [AM] IR: all, Green: off.
 * [PM] IR: all, Green: off.
 * [night] IR: all, Green: off
 * [AM]
  *
IR: PSL
  *
Green: PR2
 * [PM]
  *
IR: SR2-3 line, Xend 1F, Yend 1F
  *
Green: PR2, Xend 1F

 * [night]
  *
IR: SR2-3 line, Xend 1F, Yend 1F
  *
Green: PR2, Xend 1F
Line 92: Line 95:
 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
Line 98: Line 97:
  * Rough alignment of ETMX will be planed using IR.
Line 100: Line 98:
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa

 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.

 * week of 4/9
Line 114: Line 122:
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/27(Tue.)

  • Remote participants by eZuce: Yokozawa

Report of work (*:responsible person)

  • Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
    • All are free except for Pre-isolator.
    • Cable connections seemed to be fine.
    • First contact will be removed.
  • Oplev at ETMX: Akutsu
    • Preparation is almost done.
  • BS: *Enomoto
    • Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.

Work plan (*:responsible person)

  • Camera: *Inoue, Yokozawa
    • ETMX PD will be removed.
    • GigE camera will be removed today and placed next week.
  • Oplev at ETMX: *Akutsu, Simon
    • Once first contact is removed, opelev will be aligned.
  • BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
    • Alignment

Laser hazard

  • [AM]
    • IR: PSL
    • Green: PR2
  • [PM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 3/26
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • 3/27 EX PD will be removed.: *Yokozawa
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members