Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/5/2(Wed.) === | |
Line 51: | Line 41: |
2017/3/20(Tue.) | * Remote participants by eZuce: None * 5th day of Phase 1 operation * Noise injection, CW injection * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 53: | Line 46: |
* Remote participants by eZuce: None | |
Line 57: | Line 49: |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. * Alignment: *Izumi * All alignment to REFL after pump down was verified. |
* IFO: *Izumi, Enomoto + many * k1iy0 rebooted since timing was injected on Sunday. However coherence measurement had still problem. Missing digits of diaggui looking at k1iy0 might be a problem, but still the problem is not fixed. |
Line 64: | Line 53: |
* ETMY: *Miyamoto | * ETMX TF measurements: Miyamoto, Okutomi * 2/3 of TFs were measured well. 1/3 will be measured around the last stage of this operation if we have time. * Vibration isolation ratio was measured and matched to model pretty well. |
Line 69: | Line 60: |
* Alignment, ETMY: *Izumi * Cal: * Calibration test using MC is planned tomorrow. |
* PEM, noise injection: *Nagano, Tanaka, Miyo, Kozu, Hasegawa, Tanioka, Takano, Miyazaki, Kita, Yamamoto, Mori, Kaihotsu, Kurumiya, Ito, Tomaru, Yokozawa * CW injection |
Line 76: | Line 64: |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 82: | Line 78: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/30 * Operation continues. |
Line 88: | Line 81: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
==== Issues ==== |
Line 92: | Line 83: |
* Issues | |
Line 105: | Line 95: |
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
|
Line 131: | Line 126: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/2(Wed.)
* Remote participants by eZuce: None * 5th day of Phase 1 operation
- Noise injection, CW injection
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- k1iy0 rebooted since timing was injected on Sunday. However coherence measurement had still problem. Missing digits of diaggui looking at k1iy0 might be a problem, but still the problem is not fixed.
- ETMX TF measurements: Miyamoto, Okutomi
- 2/3 of TFs were measured well. 1/3 will be measured around the last stage of this operation if we have time.
- Vibration isolation ratio was measured and matched to model pretty well.
Work plan (*:responsible person)
- PEM, noise injection: *Nagano, Tanaka, Miyo, Kozu, Hasegawa, Tanioka, Takano, Miyazaki, Kita, Yamamoto, Mori, Kaihotsu, Kurumiya, Ito, Tomaru, Yokozawa
- CW injection
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)