Differences between revisions 352 and 353
Revision 352 as of 2018-03-20 10:41:12
Size: 9826
Comment:
Revision 353 as of 2018-03-22 09:30:44
Size: 10272
Comment:
Deletions are marked like this. Additions are marked like this.
Line 51: Line 51:
2017/3/20(Tue.) 2017/3/21(Thur.)
Line 53: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura, Miyoki
Line 57: Line 57:
 * VAC: *Uchiyama, Kimura, Suzuki
  * PR2 assembly frames will be removed soon.
 * IFO: *Izumi, Miyamoto, Eleonora
  * Daily Beam check was confirmed at the REFL port yesterday evening.
  * Measurement of BS sensing and driving matrix and diagonalizarion of them.
   * This method should be automatically performed, but still we needs some work to be done.
  * T of ETMY was checked and improved. We need the same work for L.
  * LSC screen has been updated.
Line 60: Line 64:
 * Alignment: *Izumi
  * All alignment to REFL after pump down was verified.
   * Only ETMY was off position by ~100urad.
  * AOS: *Akutsu, Yokogawa
   * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
Line 64: Line 67:
 * ETMY: *Miyamoto
  * Diagonal of sensors. Still going on.
Line 67: Line 68:
 * BS: Eleonora, Izumi
  * Coil balance is going on.

 * IMC:
  * "sleep" commands were removed from Guardian.

 * Cal: Yokozawa
  * We checked all the IMC TFs.
 * IMC, CAL: Yokozawa, Yamamoto
  * IMC Transmitted light is too low. Alignment should be checked.
  * Injection to MCE for calibration was tested.
  
 * VAC: Uchiyama
  * Vacuum level of X arm is degraded.
Line 80: Line 78:
 * Alignment, ETMY: *Izumi  * Alignment: *Izumi
  * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
   * Needs power supply for QPD.
Line 82: Line 82:
 * Cal: Yokozawa
  * Injection will be tested soon.
 * AOS: *Akutsu, Yokogawa
  * TMS alignment at ETMY.
  * Cooling will start at 10AM.
Line 87: Line 88:
 * [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
 * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
 * [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
Line 95: Line 96:
  * 3/21: Calibration test using MC.   * 3/21~: Calibration test using MC.

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/21(Thur.)

  • Remote participants by eZuce: Kimura, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • Daily Beam check was confirmed at the REFL port yesterday evening.
    • Measurement of BS sensing and driving matrix and diagonalizarion of them.
      • This method should be automatically performed, but still we needs some work to be done.
    • T of ETMY was checked and improved. We need the same work for L.
    • LSC screen has been updated.
    • AOS: *Akutsu, Yokogawa
      • Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
  • IMC, CAL: Yokozawa, Yamamoto
    • IMC Transmitted light is too low. Alignment should be checked.
    • Injection to MCE for calibration was tested.
  • VAC: Uchiyama
    • Vacuum level of X arm is degraded.

Work plan (*:responsible person)

  • Alignment: *Izumi
    • ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
      • Needs power supply for QPD.
  • AOS: *Akutsu, Yokogawa
    • TMS alignment at ETMY.
    • Cooling will start at 10AM.

Laser hazard

  • [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 4 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30          


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)