Line 51: | Line 51: |
2017/3/20(Tue.) | 2017/3/23(Fri.) |
Line 53: | Line 53: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Izumi, Miyoki |
Line 57: | Line 57: |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. |
* IFO: *Izumi, Miyamoto, Eleonora * BS had some difficulty to close control loop of Y of oplev. * T of ETMY control loop was closed. * Circuits of baffle PD are being prepared. |
Line 60: | Line 62: |
* Alignment: *Izumi * All alignment to REFL after pump down was verified. * Only ETMY was off position by ~100urad. |
* AOS: *Akutsu, Yokogawa * Green team succeeded to reach green and IR to ETMY. * BRT alignment is going on yesterday and today. * Oplev is being prepared at EXC. |
Line 64: | Line 67: |
* ETMY: *Miyamoto * Diagonal of sensors. Still going on. * BS: Eleonora, Izumi * Coil balance is going on. * IMC: * "sleep" commands were removed from Guardian. * Cal: Yokozawa * We checked all the IMC TFs. |
* Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 80: | Line 74: |
* Alignment, ETMY: *Izumi | * Alignment: *Eleonora, Miyamoto * BS diagonalization * ETMY damping |
Line 82: | Line 78: |
* Cal: Yokozawa * Injection will be tested soon. |
* AOS: *Akutsu, Yokogawa * BRT alignment is going on yesterday and today. * Oplev work at EXC. |
Line 87: | Line 84: |
* [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
* [AM] * IR: PSL * Green: around PR2 * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
Line 95: | Line 99: |
* 3/21: Calibration test using MC. | * 3/21~: Calibration test using MC. |
Line 100: | Line 104: |
* Rough alignment of ETMX will be planed using IR. | * Rough alignment of ETMX is planed using IR. |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/23(Fri.)
- Remote participants by eZuce: Izumi, Miyoki
Report of work (*:responsible person)
- IFO: *Izumi, Miyamoto, Eleonora
- BS had some difficulty to close control loop of Y of oplev.
- T of ETMY control loop was closed.
- Circuits of baffle PD are being prepared.
- AOS: *Akutsu, Yokogawa
- Green team succeeded to reach green and IR to ETMY.
- BRT alignment is going on yesterday and today.
- Oplev is being prepared at EXC.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- Alignment: *Eleonora, Miyamoto
- BS diagonalization
- ETMY damping
- AOS: *Akutsu, Yokogawa
- BRT alignment is going on yesterday and today.
- Oplev work at EXC.
Laser hazard
- [AM]
- IR: PSL
- Green: around PR2
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
- Green: Xend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21~: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX is planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools