Size: 10272
Comment:
|
Size: 10701
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/13(Fri.) === | |
Line 51: | Line 52: |
2017/3/21(Thur.) * Remote participants by eZuce: Kimura, Miyoki |
* Remote participants by eZuce: Miyoki |
Line 56: | Line 55: |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw. |
|
Line 57: | Line 58: |
* IFO: *Izumi, Miyamoto, Eleonora * Daily Beam check was confirmed at the REFL port yesterday evening. * Measurement of BS sensing and driving matrix and diagonalizarion of them. * This method should be automatically performed, but still we needs some work to be done. * T of ETMY was checked and improved. We need the same work for L. * LSC screen has been updated. * AOS: *Akutsu, Yokogawa * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order. * IMC, CAL: Yokozawa, Yamamoto * IMC Transmitted light is too low. Alignment should be checked. * Injection to MCE for calibration was tested. * VAC: Uchiyama * Vacuum level of X arm is degraded. |
* VAC: *Kimura * View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. * Damping of ETMX will be tested with HPCD. |
Line 77: | Line 64: |
* IFO: damping work or others. | |
Line 78: | Line 66: |
* Alignment: *Izumi * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX. * Needs power supply for QPD. * AOS: *Akutsu, Yokogawa * TMS alignment at ETMY. * Cooling will start at 10AM. |
* VAC: *Kimura * Pumping down will start ~10am today. |
Line 88: | Line 71: |
* [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
* [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: Upstream SR2-3 line, Yend 1F * Green: off * [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 94: | Line 85: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. |
Line 100: | Line 91: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 104: | Line 96: |
* Issues | * week of 4/23 * Operation ==== Issues ==== |
Line 117: | Line 113: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
|
Line 143: | Line 142: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/13(Fri.)
* Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
- Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
- VAC: *Kimura
- View port for oplev at ETMX was attached yesterday's afternoon.
- All the preparation was done and the door of EXC was closed.
- Damping of ETMX will be tested with HPCD.
Work plan (*:responsible person)
- IFO: damping work or others.
- VAC: *Kimura
- Pumping down will start ~10am today.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2.
- Closing EXC.
- Some controls for Michelson.
- 4/13 morning: Pump down starts.
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools