Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/20(Fri.) === | |
Line 51: | Line 52: |
2017/3/21(Thur.) * Remote participants by eZuce: Kimura, Miyoki |
* Remote participants by eZuce: None |
Line 56: | Line 55: |
* Phase 1 operation was postponed to 4/28 start and 5/6 end. | |
Line 57: | Line 57: |
* IFO: *Izumi, Miyamoto, Eleonora * Daily Beam check was confirmed at the REFL port yesterday evening. * Measurement of BS sensing and driving matrix and diagonalizarion of them. * This method should be automatically performed, but still we needs some work to be done. * T of ETMY was checked and improved. We need the same work for L. * LSC screen has been updated. |
* VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. |
Line 64: | Line 62: |
* AOS: *Akutsu, Yokogawa * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order. |
* VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. |
Line 67: | Line 65: |
* ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. |
|
Line 68: | Line 69: |
* IMC, CAL: Yokozawa, Yamamoto * IMC Transmitted light is too low. Alignment should be checked. * Injection to MCE for calibration was tested. * VAC: Uchiyama * Vacuum level of X arm is degraded. |
* ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. * BS: *Eleonora, Izumi * Implementation of L2P filter worked well and they are well decoupled now! * Global injection point for length control is ready. |
Line 78: | Line 82: |
* Alignment: *Izumi * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX. * Needs power supply for QPD. |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
Line 82: | Line 85: |
* AOS: *Akutsu, Yokogawa * TMS alignment at ETMY. * Cooling will start at 10AM. |
* VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. * Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. |
Line 88: | Line 98: |
* [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 94: | Line 112: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/16 * Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. |
Line 100: | Line 117: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
* week of 4/23 * Michelson control. * 4/28 Operation start |
Line 104: | Line 121: |
* Issues | ==== Issues ==== |
Line 117: | Line 134: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
|
Line 143: | Line 164: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/20(Fri.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- Phase 1 operation was postponed to 4/28 start and 5/6 end.
- VAC: *Kimura
- Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
- Pump down started 15:50 yesterday.
- Now vacuum gage shows ~30Pa.
- VAC: *Inoue, Yokozawa
- Vacuum monitor is ready! except for Y arm monitor.
- ETMX: *Hasegawa
- 0.07Hz was damped well!
Yaw and pitch are < 1urad.
- ETMY: *Nakano, Shishido
- Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
- Possibility of heat link for 1.6Hz still remains.
- Beam at REFL seemed to be OK.
- BS: *Eleonora, Izumi
- Implementation of L2P filter worked well and they are well decoupled now!
- Global injection point for length control is ready.
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Leak test will be performed and the gate valve will open on weekend if no problem.
- Camera: *Inoue, Yokozawa
- Tcam of Y end will be ready today.
- We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
- DMG needs some maintenance for DAQ.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check, and fix leaks.
- Opening the last gate valve weekend.
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools