Differences between revisions 353 and 402 (spanning 49 versions)
Revision 353 as of 2018-03-22 09:30:44
Size: 10272
Comment:
Revision 402 as of 2018-04-27 09:27:25
Size: 11280
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 24: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 50: Line 39:
=== 2018/4/26(Thur.) ===
Line 51: Line 41:
2017/3/21(Thur.)

 
* Remote participants by eZuce: Kimura, Miyoki
* Remote participants by eZuce: None
Line 57: Line 45:
 * IFO: *Izumi, Miyamoto, Eleonora
  * Daily Beam check was confirmed at the REFL port yesterday evening.
  * Measurement of BS sensing and driving matrix and diagonalizarion of them.
   * This method should be automatically performed, but still we needs some work to be done.
  * T of ETMY was checked and improved. We need the same work for L.
  * LSC screen has been updated.
 * IFO: *Izumi, Enomoto + many
  * Michelson lock lasted longer than 2 and half hours!
  * Alignment control from IFO to ETMX was implemented by dithering ETMX.
  * PR3 alignment was implemented by baffle signal.
  * ETMX damping might be a cause of lock lost.
  * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
  * BS oplev is fed back to not only TM but also IM. (Arai)
Line 64: Line 53:
  * AOS: *Akutsu, Yokogawa
   * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
 * WAB: *Akutsu
  * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
  * Equilibrium temperature was 21K.
  * Damping became to strong in low temperature.
Line 67: Line 58:
 * Wire of RM was broken on SR3 during tightening clamp.
Line 68: Line 60:
 * IMC, CAL: Yokozawa, Yamamoto
  * IMC Transmitted light is too low. Alignment should be checked.
  * Injection to MCE for calibration was tested.
  
 * VAC: Uchiyama
  * Vacuum level of X arm is degraded.
 * CAL: *Yamamoto
  * Line injection is being tested.
  * UGF serve will not be implemented, so change of optical gain is compensated in off line.
Line 75: Line 64:
 * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened.
 * Operation schedule and emergency contact list is put on the white board in the control room.
Line 78: Line 69:
 * Alignment: *Izumi
  * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
   * Needs power supply for QPD.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 82: Line 72:
 * AOS: *Akutsu, Yokogawa
  * TMS alignment at ETMY.
  * Cooling will start at 10AM.
 *
Line 88: Line 76:
 * [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [night] IR: SR2-3 line, Yend 1F. Green:  Yend 1F.
 * [AM]
  *
IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  *
Green: PR2, Xend 1F
 * [PM]
  *
IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  *
Green: PR2, Xend 1F

 * [night]
  *
IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  *
Green: PR2, Xend 1F
Line 94: Line 90:
 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 100: Line 94:
 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
==== Issues ====
Line 104: Line 96:
 * Issues   * PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
  * PR3 also had jumps caused by DAC glitches.
Line 117: Line 110:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
Line 143: Line 140:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/26(Thur.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • Michelson lock lasted longer than 2 and half hours!
    • Alignment control from IFO to ETMX was implemented by dithering ETMX.
    • PR3 alignment was implemented by baffle signal.
    • ETMX damping might be a cause of lock lost.
    • ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
    • BS oplev is fed back to not only TM but also IM. (Arai)
  • WAB: *Akutsu
    • Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
    • Equilibrium temperature was 21K.
    • Damping became to strong in low temperature.
  • Wire of RM was broken on SR3 during tightening clamp.
  • CAL: *Yamamoto
    • Line injection is being tested.
    • UGF serve will not be implemented, so change of optical gain is compensated in off line.
  • Operation wiki page is opened.

  • Operation schedule and emergency contact list is put on the white board in the control room.

Work plan (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

  • PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
  • PR3 also had jumps caused by DAC glitches.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)